Natural Hydrogen and Helium Formation Continuity in Ramsay 4
Released
Released
Announcement PDF
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
| 1
16 December 2025
ASX Announcement
Ramsay Project Operational Update
Significant Natural Hydrogen and Helium Gas Formation
Continuity in Ramsay 4
Highlights:
On the back of the strategic investment from Toyota Motor Corporation, Mitsubishi Gas
Chemical and ENEOS Xplora, Ramsay 4 has been drilled to a total depth of 855m. This is the
second successful well drilled in the Company’s 2025 drilling campaign.
Ramsay 4 was drilled 500m away from Ramsay 2, and successfully penetrated a number of
highly porous and permeable zones within the Parara, Kulpara and Winulta Formations.
Formation evaluation of Ramsay 4 highlights strong lateral correlation with Natural
Hydrogen and Helium bearing formations that were sampled and tested in Ramsay 1 and 2.
This preliminary interpretation highlights the potential for a significant Natural Hydrogen
and Helium resource base.
Baker Hughes wireline data also indicates Ramsay 4 has penetrated thick gross formation
intervals within the Kulpara Dolomite and Winulta Sandstone sections where Helium
concentrations up to 36.9% (air and nitrogen corrected) were seen from the Ramsay 1
extended flow test in August 2024.
The Natural Hydrogen and Helium bearing reservoir properties in the Ramsay Project
appear to be aligned with other global Natural Hydrogen and Helium field developments,
based on the preliminary technical analysis of the wireline logs.
Multiple samples of mud-gas and wellhead gas have been collected for third party
laboratory analysis, and ongoing interpretation of the results for Ramsay 4 will continue.
The Ramsay 4 well will be suspended for near term testing where the Company plans to
maximise fluid flow rates during its Completions and Well Test Program (in late Q1 2026),
which will form the basis for the Ramsay field development plan.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
| 2
Gold Hydrogen Managing Director, Neil McDonald said: “The Ramsay 4 results are very
encouraging and demonstrate the further extension of the Natural Hydrogen and Helium systems
across the Ramsay Project area. This information will be instrumental in decisions around a
potential pilot project development and Ramsay commercialisation strategy. With the support of
our Strategic Investors, we look forward to our upcoming testing program starting in Q1 2026,
where we plan to determine flow rate potential, a significant milestone in preparation for future
Ramsay field development plans.”
The Directors of Gold Hydrogen Limited (Gold Hydrogen, ASX: GHY, the Company) are pleased to provide
a preliminary operational update on the Ramsay 4 well.
Drilling at Ramsay 4 commenced on 3 December 2025, this being the fourth dedicated Natural Hydrogen
and Helium exploration well in Australia, and a follow-up to the successful Ramsay 1, 2 and 3 wells. The
Ramsay 4 well is located 500m away from the Ramsay 2 well (see Figure 1). Over the past 2 weeks, the
surface casing on Ramsay 4 was set at 180.9m at the top of the Parara Limestone section. The well was
then drilled to a total depth of 855m on 13 December 2025, to the top of the Hiltaba Granite.
A full suite of high-quality wireline logs including Nuclear Magnetic Resonance (NMR), acoustic and
resistivity imaging logs has been acquired. Multiple samples of mud-gas were taken throughout the Parara
Formation and wellhead gas samples were also collected while drilling continued below a mud losses zone
encountered at approximately 330m. This zone is interpreted to be the same interval penetrated in
Ramsay 1 which showed excellent fracture connectivity and provides confidence for the potential of future
successful flow testing. Third party laboratory analysis of samples collected is ongoing and will continue
to be integrated into the Ramsay 4 evaluation and subsurface models.
Preliminary results and interpretation of Baker Hughes wireline logs indicate continuity of several stacked
porous and permeable gas bearing zones found in Ramsay 1 and 2. In Ramsay 4, elevated levels of Natural
Hydrogen were measured from mudgas through the SLB DQ1000 gas chromatograph within the Parara
Formation, and wireline log interpretation highlights a 310m gross formation thickness with strong gas
anomalies from NMR log analysis. Refer Table 1.
The Company’s interpretation of the Baker Hughes wireline logs for the deeper Kulpara Formation indicate
a combined gross formation thickness of 180m which correlates to the tested Helium zones in Ramsay 1
and 2 where purities of up to 36.9% were measured on an air and nitrogen corrected basis. Refer Table 2
appended from previous testing. Interpretation of NMR logs indicate several gas bearing intervals with
good porosity and permeability characteristics throughout the Kulpara Dolomite and Winulta Sandstone.
Wireline logs from all four wells drilled to date indicate excellent correlation and formation continuity
across the Ramsay Project area. This interpretation will form the basis for future volumetric assessments
and potential Ramsay field development plans. The Natural Hydrogen and Helium bearing reservoir
properties in the Ramsay Project appear to be aligned with other global Natural Hydrogen and Helium field
developments based on the preliminary technical analysis of the wireline logs.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
| 3
Planning is underway for the Ramsay 4 well to be completed by installing an Electronic Submersible Pump
(ESP) and production testing with a temporary surface production facility, which will also have a gas
compressor integrated. The Completions and Well Test Program is scheduled to take place in late Q1 2026
following the completion of the drilling campaign, and the scope will be finalized once formation
evaluation datasets have been fully integrated from all wells. The Completions and Well Test Program will
be a test of the Natural Hydrogen and Helium flow potential of all prospective formations intersected in
the Ramsay Project area to date.
The Condor Energy Services Rig #1 is in the process of being demobilised from the Ramsay Project area,
and the focus will now shift to preparing for the Completions and Well Test Program which is scheduled
to take place in late Q1 2026.
Figure 1: Location of the Ramsay 4 well in relation to the Ramsay 1 and Ramsay 2 wells drilled by the
Company in 2023
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
| 4
Image 2: Ramsay 4 wellsite during drilling
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
| 5
Table 1 – Listing Rule 5.30 Information (Preliminary)
Name: Ramsay 4
Location (UTM zone 53
GDA2020)
X 747787 mE
Y 6149863 mN
Permit PEL 687
Entity holders(s) Gold Hydrogen 100%
Resources Hydrogen, Helium
Formation Parara, Kulpara Limestone, Kulpara Dolomite, Winulta Sandstone
Gross thickness and net pay
thickness
Parara 310m gross, Kulpara Limestone 130m gross, Kulpara
Dolomite 180m gross, Winulta Sandstone 60m gross
Geological rock type Limestones, Dolomites, Dolomitic Sandstones
Depth of the zones tested
Parara 160 – 450m, Kulpara Limestone 450 – 580m, Kulpara
Dolomite 580 – 760m.580-760, Winulta Sandstone 760 – 820m
Type of test and duration Calibrated mud gas log data, Isotubes, wireline log data
Phase recovered Gas/water
Other types of recovery N/A
Flow rates, choke size, volumes
recovered
N/A
Fracture stimulation N/A
Material non hydrocarbons Hydrogen, Helium, Nitrogen, CO2
Insufficient information is presently available to determine net pay thickness.
Important Risk Commentary
It is important to note that there remain both geological and potential development risks associated with
the Ramsay Project and the Company’s commercial and business objectives. These risks relate to the
presence, recovery and potential volumes of both Natural Hydrogen and Helium, but also due to the
location of the gas systems within agricultural areas and the proximity to National Parks on both Yorke
Peninsula and Kangaroo Island, requiring significant landholder and community engagement. The
worldwide, Federal and South Australian Government and industry efforts to secure Hydrogen as an
alternative energy source provides confidence that any technical and social concerns may be overcome.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
| 6
About Gold Hydrogen
Gold Hydrogen is focused on the discovery and development of world class Natural Hydrogen and Helium
gases in a potentially extensive province in South Australia. This region had its Natural Hydrogen and
Helium potential confirmed by the Company via its maiden 2023 / 24 drilling and well testing campaigns.
The domestic and global demand for Hydrogen and Helium, combined with new exploration techniques
and experienced personnel, provides Gold Hydrogen with an extraordinary opportunity to define and
ultimately develop a new Natural Hydrogen and Helium gas province.
The combined natural hydrogen permit area of the Gold Hydrogen group is in excess of 75,000km2
. Gold
Hydrogen holds one granted petroleum exploration license (the Ramsay Project - PEL 687) and its two
100% owned subsidiary companies (White Hydrogen Australia and Byrock Resources) hold an additional
seven (7) applications for Natural Hydrogen and Helium exploration within South Australia.
The Company’s Prospective Resource Statements are appended as Tables 3 and 4 appended.
Gold Hydrogen is also the preferred applicant for four (4) gas storage exploration licenses applications
(GSELA) covering an area of 8,107km2
within the Yorke Peninsula portion of PEL 687 in South Australia.
These storage licence applications are in addition to the granted exploration licence and application
licences. A 100% owned Gold Hydrogen subsidiary, Sustainable Minerals Group Pty Ltd, also holds a
mineral lease on the Yorke Peninsula potentially prospective for iron-oxide, copper and / or gold
mineralisation.
The group’s permit areas are characterised by low population densities, cooperative stakeholders and
aspects of the natural environment suited to the exploration and development of a future natural
hydrogen gas province. Gold Hydrogen places considerable importance on close liaison with landholders,
traditional owners and all other stakeholders, and this approach has led to the grant of its key tenement
PEL 687 in South Australia. The Company intends to continue to invest in these efforts.
Further Information
Further information on the Gold Hydrogen group, its projects, and its Board and Management can be found
on the Company’s website (www.goldhydrogen.com.au) together with a copy of the Company’s
Replacement Prospectus of 29 November 2022.
Gold Hydrogen also has accounts on LinkedIn and Twitter (@GHY_ASX), and copies of market releases will
be emailed to all interested parties who register via info@goldhydrogen.com.au
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
| 7
This announcement has been authorised for release by the Managing Director.
On behalf of the Board
Karl Schlobohm
Company Secretary
For Company Enquiries Contact:
Neil McDonald – Managing Director Karl Schlobohm – Company Secretary / CFO
nmcdonald@goldhydrogen.com.au kschlobohm@goldhydrogen.com.au
+61 7 3521 8038 +61 7 3521 8038
For Media Enquiries Contact:
Matthew Doman – Crestview Strategy
matthew.doman@crestviewsrtrategy.com
+61 421 888 858
Prospective Resource Statements
The Prospective Resource Statements for Natural Hydrogen and for Helium have been included in this
announcement under the approval of Mr Billy Hadi Subrata, Chief Technical Officer for Gold Hydrogen,
who is a Qualified Petroleum Reserves and Resources Evaluator. Mr Hadi Subrata confirms that, as at the
date of this announcement, there are no changes to information or additional information, since the
effective dates, that would materially change the estimates of prospective resources quoted.
Forward Looking Statement / Future Performance
This announcement may contain certain forward-looking statements and opinion Forward-looking
statements, including projections, forecasts and estimates, are provided as a general guide only and should
not be relied on as an indication or guarantee of future performance and involve known and unknown
risks, uncertainties, assumptions, contingencies and other important factors, many of which are outside
the control of the Company and which are subject to change without notice and could cause the actual
results, performance or achievements of the Company to be materially different from the future results,
performance or achievements expressed or implied by such statements. Past performance is not
necessarily a guide to future performance and no representation or warranty is made as to the likelihood
of achievement or reasonableness of any forward-looking statements or other forecast. Nothing contained
in this announcement, nor any information made available to you is, or and shall be relied upon as, a
promise, representation, warranty or guarantee as to the past, present or the future performance of Gold
Hydrogen Limited.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
| 8
Table 2 – Helium Sample Analysis Table – Ramsay 1 Well – Stage 2 (originally released 17 October 2024)
Name: Ramsay 1
Location (UTM zone 53 GDA2020)
X 748,208.07
Y 6149545.7
Permit PEL687
Entity holders Gold Hydrogen 100%
Zones tested Zone 2 and 3
Resources Helium
Formation Kulpara Dolomite
Gross thickness and net pay
thickness
180m Gross
Geological rock type Dolomite
Depth of the zones tested 900 mMD
Type of test Commingled pressure test
Phase recovered Gas/Water
Corrected H2 and He concentration
in gas recovered from downhole
sample
36.9% He
Flow rates, choke size, volumes
recovered
1 Mscf/day gas constraint by pump capacity
and flow intermittently with water; choke size
20/64 inch; volumes recovered 0.55 Mscf
Fracture stimulation None
Material non hydrocarbons Nitrogen, Hydrogen
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
| 9
Table 3 – Prospective Resource Statement for Natural Hydrogen
Gold Hydrogen’s Ramsay Project: Prospective Resources* of Hydrogen in ‘000 Tonnes – 30 Sept 2021
PEL Prospects
SPE
PRMS
Sub-
class
1U
Low
Estimate
2U
Best
Estimate
Mean
3U
High
Estimate
Pg Pd Pc
PEL 687
All
Prospects
and Leads
207 1,313 4,187 8,820 22% 48% 10%
Yorke
Peninsula
PEL 687 Ramsay FB Prospect 124 931 2,712 6,989 22% 50% 11%
PEL 687 Ramsay Lst Prospect 10 70 191 492 26% 50% 13%
PEL 687 Maitland Lead 7 26 40 92 17% 35% 6%
Kangaroo
Island
PEL 687 Navigator Lead 34 152 280 678 19% 40% 8%
PEL 687 Kanmantoo Prospect 32 134 237 569 25% 40% 10%
* This estimate of Natural Hydrogen Prospective Resources must be read in conjunction with the notes
below, and it should be noted that the estimated quantities of Natural Hydrogen that may potentially
be recovered by the application of a future development project(s) relate to undiscovered
accumulations. These estimates have both an associated risk of discovery and a risk of development.
Further exploration, appraisal and evaluation is required to determine the existence of a significant
quantity of potentially recoverable Natural Hydrogen.
Notes:
1. This reserves statement presents Gold Hydrogen’s Prospective Resources. Gold Hydrogen currently
has no Reserves and no Contingent Resources.
2. Estimates are assessed to comply with the ASX Listing Rules for Prospective Resources and SPE-PRMS
2018 with the understanding that naturally occurring hydrogen may be considered a hydrocarbon
since it has energy content and can be used stand alone and/or blended with sales gas. “U” implies
Prospective Resources.
3. Per ASX Listing Rules 5.28.4 and 5.28.5 estimates are unrisked and aggregated arithmetically by
category, hence caution that the aggregate low estimate may be a very conservative estimate and the
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
| 10
aggregate high estimate may be a very optimistic estimate due to the portfolio effects of arithmetic
summation.
4. Probabilistic methods are used to prepare the estimates. The distribution of the estimates is the “full
distribution” and has not been truncated by application of the MEPS (minimum economic pool size
concept).
5. The Reference Point is at the wellhead/edge of lease (i.e. wellhead facilities) so the estimates have
no deduction for flare, vent or fuel consumed in operations.
6. Pg (Chance of Geologic Discovery), Pd (Chance of Development) and Pc (Chance of Commerciality =
Pg x Pd) are calculated as a weight average of the P50’s of the H2 (‘000 Tonnes) of the prospects.
7. Pg incorporates Play Risk and Prospect Risk.
8. Pd incorporates an assessment across all SPE-PRMS Commerciality Criteria (i.e. not just economics).
9. Information in the table is rounded. Some totals in the tables may not add due to rounding.
10. This reserves statement:
a. is based on, and fairly represents, information and supporting documentation prepared by the
qualified petroleum reserves and resources evaluators listed in note 14 below. Details of each
qualified petroleum reserves and resources evaluator’s employment and professional
organisation membership are set out in note 14 below;
b. has been approved by Luke Titus, who is a qualified petroleum reserves and resources evaluator
and whose employment and professional organisation membership details are set out in note 14
of this reserves statement;
c. is issued with the prior written consent of Luke Titus and Teof Rodrigues & Associates (“TRA” -
involving Teof Rodrigues, Paul Strong, and Greg Horton, whose employment and professional
organisation membership details are set out in note 14 of this reserves statement) as to the form
and context in which the estimated Natural Hydrogen resources and the supporting information
are presented.
11. There is no change to information or additional information, since the effective date of 30 September
2021, that Gold Hydrogen and TRA are aware of that would materially change the estimates in this
reserves statement.
12. Gold Hydrogen engages independent experts TRA to evaluate reserves and resources.
13. Qualified Petroleum Reserves and Resources Evaluators are:
Name Employer* Professional organisation
Luke Titus Gold Hydrogen SPE
Teof Rodrigues Teof Rodrigues & Associates SPE, PESA
Paul Strong Teof Rodrigues & Associates GSL, AAPG, PESA
Greg Horton Teof Rodrigues & Associates SPE
* As at 30 September 2021
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
| 11
Table 4: Prospective Resource Statement for Helium
Gold Hydrogen Prospective Resources* of Helium in Bcf - Ramsay Project (PEL 687 Yorke Peninsula) 21 February 2024
PEL Prospects
SPE
PRMS
Sub-
class
Formation
1U
Low
Estimate
2U
Best
Estimate
Mean
3U
High
Estimate
Pg Pd Pc
PEL 687
All
Prospects
All Formations
Total
7 41 96 243 17% 60% 10%
PEL 687
Ramsay
Fault Block
Prospect
Kulpara Formation 0.8 3.6 7.0 17.1 29% 60% 17%
Winulta Formation 0.1 0.6 1.6 4.0 12% 60% 7%
Fractured Basement 0.7 3.8 6.9 16.7 13% 60% 8%
Total 2 8 15 38 20% 60% 12%
PEL 687
South of
Ramsay
Fault Block
Prospect
Kulpara Formation 2.1 12.8 30.5 77.6 23% 60% 14%
Winulta Formation 0.3 2.4 7.7 19.8 8% 60% 5%
Fractured Basement
Hilbata Suite
1.6 10.3 25.5 65.2 12% 60% 7%
Fractured Basement
Yorke Peninsula Heel
1.4 7.7 17.0 42.7 12% 60% 7%
Total 5 33 81 205 16% 60% 10%
* This estimate of Helium Prospective Resources must be read in conjunction with the notes below.
These Helium Prospective Resources are estimated quantities of Helium that may potentially be
recovered by the application of a future development project(s) relate to undiscovered accumulations.
These estimates have both an associated risk of discovery (Pg) and a risk of development (Pd). Further
exploration, appraisal and evaluation is required to determine the existence of a significant quantity of
potentially recoverable Helium.
Notes:
1. This table presents Gold Hydrogen's Prospective Resources for Helium in the Ramsay Field of Yorke
Peninsula only. Gold Hydrogen currently has no Reserves and no Contingent Resources.
2. Estimates are assessed to comply with the ASX Listing Rules for Prospective Resources and SPE-PRMS
2018. SPE have provided guidance regarding the Extension of PRMS Principles to Non-
Hydrocarbon/Non-Traditional Situations including Helium (and Hydrogen).
Refer: https://www.spe.org/en/industry/reserves/non-hydrocarbons/
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
| 12
3. Per ASX LRs 5.28.4&5 estimates are unrisked and aggregated arithmetically by category, hence
caution that the aggregate low estimate may be a very conservative estimate and the aggregate high
estimate may be a very optimistic estimate due to the portfolio effects of arithmetic summation.
4. Probabilistic methods are used to prepare the estimates. The distribution of the estimates is the "full
distribution" and has not been truncated by application of the MEPS (minimum economic pool size)
concept.
5. The Reference Point is at the wellhead/edge of lease (i.e. wellhead facilities) so the estimates have
no deduction for flare, vent or fuel consumed in operations.
6. Pg (Chance of geologic Discovery), Pd (Chance of Development) and Pc (Chance of Commerciality =
Pg x Pd) are calculated as a weight average of the P50's of the Helium Bcf (Billion Cubic Feet) of the
prospect formations.
7. Pg incorporates Play Risk and Prospect Risk.
8. Pd incorporates an assessment across all SPE-PRMS Commerciality Criteria (i.e. not just economics).
9. Information in the table and throughout the Report is rounded. Some totals in the tables may not add
due to rounding.
10. There is no change to information or additional information, since the effective date of 21 February
2024, that Gold Hydrogen and TRA are aware of that would materially change the estimates in this
reserves statement.
QPRRE Statement
The Prospective Resource Statement in this announcement is based on, and fairly represents, information
and supporting documentation prepared by independent consultants “Teof Rodrigues & Associates” (Mr
Teof Rodrigues, Mr Paul Strong and Mr Greg Horton) and Mr Billy Hadi Subrata, Chief Technical Officer for
Gold Hydrogen, with an effective date of 21 February 2024.
The Prospective Resource Statement has been included in this announcement:
(1) under the approval of Mr Billy Hadi Subrata, Chief Technical Officer for Gold Hydrogen, who is a
Qualified Petroleum Reserves and Resources Evaluator; and
(2) with the prior written consent of Mr Billy Hadi Subrata and “Teof Rodrigues & Associates” (Mr Teof
Rodrigues, Mr Paul Strong and Mr Greg Horton) as to the form and context in which the helium
prospective resource statement and supporting information are presented.
The employment and professional organisation membership details of Mr Billy Hadi Subrata, Mr Teof
Rodrigues, Mr Paul Strong and Mr Greg Horton are as follows:
Name Employer Professional organisation
Billy Hadi Subrata Gold Hydrogen SPE
Teof Rodrigues Teof Rodrigues & Associates SPE, PESA
Paul Strong Teof Rodrigues & Associates GSL, AAPG, PESA
Greg Horton Teof Rodrigues & Associates SPE