Project and Corporate Update
Released
Released
Announcement PDF
Gold Hydrogen Limited | ABN 74 647 468 899 | goldhydrogen.com.au | info@goldhydrogen.com.au
Level 14, 110 Eagle Street (GPO Box 801) Brisbane, QLD 4000
14 October 2025
ASX Announcement
Project and Corporate Update
Highlights:
Following the provision of funding from the $14.5m strategic investment made by Toyota
Motor Corporation, Mitsubishi Gas Chemical Inc and ENEOS Xplora Inc, the Company’s 2025
/ 26 drilling and well testing campaign is due to commence with the Ramsay 3 exploration
well scheduled for spudding on or around 6 November 2025.
The 2025 / 26 work program is designed to:
o delineate and confirm the presence and scale of Natural Hydrogen and Helium across
other parts of the exploration lease (PEL687), based on 2D seismic and the successful
findings at Ramsay 1 and 2 wells;
o provide optimal conditions for well testing and extracting Natural Hydrogen and
Helium to surface;
o mature the Ramsay Project via further appraisal in preparation for potential
commercial development decisions; and
o assist with the development of a blueprint for future exploration and appraisal
initiatives across the Company’s wider portfolio.
The Company has bolstered its management team via the appointment of a number of key
team Members ahead of launching the 2025 / 26 drilling and well testing campaign,
including Simon Talbot as Chief Commercial Officer.
A number of potential commercial development pathways are in the process of being
identified, with studies and conceptual design work to follow on from the 2025 / 26 drilling
and testing program. Some of these initiatives leverage the industry knowledge and
experience of the Company’s strategic investors.
Fluid inclusion studies have commenced on the group’s application permits. The results will
be combined with available seismic data to assist with the delineation of areas of interest
and future drill targets across the portfolio.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
The Directors of Gold Hydrogen Limited (Gold Hydrogen, ASX: GHY, the Company) are pleased to provide
the following update on the Company’s planned project activities and corporate developments.
Project Related Activity Update
Ramsay Project – 2025 Exploration Drilling Program
Following Gold Hydrogen’s successful drilling campaign in late 2023, the Company will continue its
exploration activities with drilling to commence at the Ramsay 3 exploration well in early November 2025.
For this upcoming program, the Company is planning to drill two or three wells to appraise specific target
zones within identified structures, chosen with reference to the results of the maiden drilling and testing
campaign, as well as the interpretations leading from the 2D seismic survey conducted in the second half
of 2024.
The primary objectives for the 2025 drilling program are to:
1. delineate and confirm the presence of Natural Hydrogen and Helium beyond the successful Natural
Hydrogen and Helium gas shows at the Company’s Ramsay 1 and 2 wells;
2. provide optimal conditions for well testing and extracting Natural Hydrogen and Helium to surface;
3. mature the Ramsay Project via further appraisal in preparation for potential commercial development
decisions; and
4. assist with the development of a blueprint for future exploration and appraisal initiatives across the
Company’s wider portfolio.
A significant amount of data was gathered during the previous drilling and testing program which
concluded in mid-2024, and a detailed review and analysis of that data has now been concluded. That
work, combined with the 2D seismic survey interpretation, has resulted in the plan for the Company’s 2025
/ 26 drilling and well testing program which will commence with the Ramsay 3 well to be drilled up-dip
and approximately 2km from the Ramsay 1 well, on a geological structural high in the area.
The Ramsay 1 and 2 exploration wells were drilled to confirm the presence of Natural Hydrogen, and the
location of those wells was deliberately selected adjacent to the historic Ramsay Oil Bore 1 drilled in 1931
which had Hydrogen shows recorded. Based on the results of the 2023 / 24 campaign, the 2D seismic
survey analysis and other information, the Company considers the Ramsay 3 well location to be more
optimal, and up-dip from the previous wells.
Subject to the results of the Ramsay 3 drilling, a further one or two wells are planned for this drilling
campaign. These will be in relatively close proximity to Ramsay 1, 2 and 3 with a view toward establishing
a pilot project in this area, subject to results.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
Figure 1: Map showing Ramsay well locations (existing and planned) relative to 2D seismic lines
The Ramsay 1 and 2 exploration wells were designed with small diameter well bores and a 4 ½” casing to
keep costs as low as practical whilst still being able to run logging tools to gather data, and to specifically
verify the presence of Natural Hydrogen adjacent to the historic 1931 Ramsay Oil Bore location. In the
Company’s 2023 drilling campaign, not only was the presence of Natural Hydrogen confirmed (at air-
corrected purity levels up to 95.8%1), the presence of Helium was also confirmed (at air-corrected purity
levels up to 36.9%2 ), as well as elevated levels of Helium-33 , significantly adding to the potential
commercialisation options for the Ramsay Project.
Following the positive drilling results from drilling the Ramsay 1 and 2 wells, the Company carried out well
testing activities to gain knowledge of the reservoir characteristics. Much data was gathered and the
findings from the tests has also contributed to the well design for this 2025 / 26 program. A key impact
on the testing of the Ramsay 1 and 2 wells was the limited ability to dewater the wells due to the restricted
approvals and testing timelines.
The well design for the 2025 / 26 campaign includes a larger diameter well bore with 7” casing to enable
greater flexibility for well testing. The data expected to be gathered from the drilling and testing of the
wells in the Company’s 2025 / 26 program will inform potential future pilot project area(s) and design(s),
with the aim of demonstrating the commercial production potential of both Natural Hydrogen and Helium
from the Ramsay Project.
1
Refer ASX release of 27 May 2024 for full details. Technical table also appended.
2
Refer ASX release of 17 October 2024 for full details. Technical table also appended.
3
Refer ASX release of 30 October 2024 for full details. Technical table also appended.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
Ramsay Project – 2026 Exploration Well Testing Campaign
The Company intends to test Ramsay 3, and potentially Ramsay 4 and 5, during 2026. The detailed
planning for well testing is underway, and will be refined based on the results from drilling. The well testing
program is currently scheduled to commence in Q1 2026. The objective of the well testing includes the
movement of both Natural Hydrogen and Helium to surface under conditions designed to support
conceptual designs and studies for one or more pilot projects to demonstrate potential project viability
for both Natural Hydrogen and Helium production, and to gather further data from the sampling of fluid
and gas during the testing operations.
Ramsay Project – Potential 2026 Resource Delineation Drilling and Regional Targets
The 2D seismic survey carried out in 2024 revealed several regional Natural Hydrogen and Helium
prospects within PEL 687, some of which will be tested with future dedicated exploration wells. The
selection and timing of these regional exploration wells may be undertaken in conjunction with planned
further appraisal / delineation drilling activities. The anticipated timing for this workstream is mid to late
2026.
Ramsay Project – Green Methanol Feasibility Study
Gold Hydrogen is actively assessing a number of potential commercial opportunities for a successful
development of the Ramsay Project, including green ammonia and green methanol, as well as pure Natural
Hydrogen and Helium gas options. Green methanol is a key fuel choice for decarbonising shipping and
aviation because it is liquid at room temperature, making it easier to store and transport than gaseous
Hydrogen, and its use in existing or easily converted engines results in significant lifecycle CO2 emission
reductions. Major shipping companies are currently ordering methanol-ready ships, and investing in green
methanol production to meet net-zero targets.
The Yorke Peninsula is very well placed to be a global green methanol production hub with abundant waste
agricultural biomass (biogenic carbon) and renewable energy sources. Critical to the production of green
methanol is cost-competitive Hydrogen, which the Company is striving to bring to commercialisation via
its Ramsay Natural Hydrogen and Helium Project.
The production of green methanol made using Natural Hydrogen is expected to have commercially
competitive advantages over green methanol produced via electrolysis-derived (ie. man-made) Hydrogen,
based on the evidence available from the Bourakebougou Natural Hydrogen Field in Mali. Gold Hydrogen’s
Ramsay Project has a significant prospective resource of Natural Hydrogen (refer Table 5 appended) which
it is aiming to advance via the technical programs outlined above.
An initial analysis of the biogenic carbon sources in and around the Yorke Peninsula indicate a readily
available supply of up to 1.5 million wtpa (wet tonnes per annum) of compliant biomass4
. Furthermore,
long-term renewable energy pricing (solar / wind / BESS (battery energy storage systems)) indicates that
a project on the Yorke Peninsula can be supplied at economic rates via the electricity network5
. Port
infrastructure and capacity is also available on the Yorke Peninsula (eg. Port Giles, Ardrossan) for importing
and exporting activities.
4
South Australian Crop and Pasture Report 2024-25, January 2025.
5
Australian Energy Market Operator, 2024 ELI Report, June 2024 (Appendix 5 – South Australia).
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
Gold Hydrogen plans to assess all of these factors in detail and complete a Feasibility Assessment of the
green methanol opportunity, and has appointed Mr Simon Talbot to help spearhead this initiative (refer
below). Based on the results of the Feasibility Assessment, a pilot plant will be considered and costed for
initial production.
Current Green Methanol pricing is USD850-1,050 per tonne6
, and is already in use within the international
shipping industry.
The Company will provide more detailed updates on this initiative once the Feasibility Assessment
commences.
Regional Application Areas – Preliminary Studies
The Company continues to progress several of its application areas towards granted status via the ongoing
advancement of Native Title related matters. In addition, the Company continues with its desktop analysis
of the publicly available South Australian Resource Information Gateway (SARIG) datasets, as well as a
range of historical information, to compile a preliminary subsurface data suite.
The focus of this activity is on transposing the learnings to date from the Ramsay Project to identify Natural
Hydrogen exploration focus areas within its regional application portfolio in South Australia.
Initial technical areas where learnings from the Ramsay Project are being applied include:
Analysis of the regional tectonic and geological settings;
Petrophysical, stratigraphic and basement studies;
Impact of fracture zones and structural boundaries;
Seal and trap potential within different geological domains;
Analysis of the potential for radiolytic and / or iron-bearing alteration sources in the basement suites;
Analysis of historic core samples for potential Natural Hydrogen and Helium within fluid inclusions
(refer below);
Preliminary interpretation of the GA seismic line data (refer below).
Historic Core Samples and Study of Fluid Inclusions
Gold Hydrogen geologists have recently made several visits to the South Australian Drill Core Library to
review and gather samples from historic third-party drill cores from within several of the group’s regional
application areas for testing and analysis. The aim of the testing of these core samples will be to detect
any Natural Hydrogen and Helium in paleo-fluid inclusions, similar to the previous campaign undertaken
by the Company for PEL 687 in 2023. The findings will help to identify promising areas within the
application areas for gas generation and migration in order to guide further geological studies and future
on-ground exploration efforts.
6
Methanol Institute: Methanol Institute (2024). "Economic Value of Methanol for Shipping under FuelEU Maritime
and EU ETS." Analysis by Dr. Jeroen Dierickx.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
The results for the core sample analysis for the PELA 688 application area are expected in the next weeks,
followed by a number of the White Hydrogen Australia application areas, and then PELA 792.
The results of the fluid inclusion studies will be combined with an analysis of the Geoscience Australia
seismic data available (refer below) to assist with the delineation of areas of interest and future drill targets
across the application area portfolio.
Formal on-groundwork programs will commence on each application area as they are granted.
Figure 2: Map showing the fluid inclusion study points across the group’s application areas.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
Geoscience Australia Seismic Line
Geoscience Australia released the data associated with a regional seismic line acquired in 2022 along public
roads which transverses part of the Gold Hydrogen group’s application footprint (specifically PELA’s 792,
703 and 702), as outlined in Figure 3 and Figure 4 below.
Figure 3: Map showing the GA seismic line transversing a number of the group’s application areas.
Gold Hydrogen Limited | ABN 74 647 468 899 | goldhydrogen.com.au | info@goldhydrogen.com.au
Level 14, 110 Eagle Street (GPO Box 801) Brisbane, QLD 4000
Figure 4: Cross Section of the Geoscience Australia Seismic Line Traversing Part of the Group’s Application Areas
A’
A
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
Corporate Update
Appointment of Chief Commercial Officer
The Company is pleased to announce the appointment of Simon Talbot as Chief Commercial Officer.
Simon will join the Company having just finalised the successful sale of the $1.9B Green Methanol / Green
Hydrogen project at Bell Bay Tasmania. He is a passionate advocate for utilising Australia’s sustainable
competitive advantages and the enormous potential for Natural Hydrogen and biomass to be combined
to make low carbon liquid fuels.
Simon is well known to Japanese and North American investment groups, and has worked for over 25 years
across renewables as an Agribusiness Executive for some of Asia Pacific’s leading companies including Kraft
Foods, Australian Paper, Cadbury, Glencore and Coles Group.
Simon holds a BSc Earth Sciences, MBA UNSW and is a GAICD.
Appointment of Additional Technical Team Members
The Company has bolstered its Natural Hydrogen expertise by appointing geologist Hugo Beldame to work
with the existing geological and technical team in Brisbane and Perth.
Hugo has previously worked for 2H Resources and French Company 45-8 Energy, where he was involved
with various geological work program designs and field execution.
Hugo holds Masters Degrees in Petroleum Geology (France) and Geoscience Exploration (Norway).
In addition, the Company has appointed Leon Hennessey under a contract arrangement to act as the
Company’s General Manager of Operations to oversee the Ramsay Project’s 2025 drilling and 2026 well
testing campaigns as outlined above.
With broad industry experience working in most major energy markets, Leon has practical hands-on
experience throughout the well construction life cycle encompassing project management, engineering,
and optimization.
Since 2010, Leon has held various senior management positions for Eastern Hemisphere markets including
National Oilwell Varco as Director of Drilling Automation & Optimisation, and ModuSpec as Regional
Director. As an upstream consultant focussed on Projects, Drilling and Wells he delivered projects
successfully in multiple markets focussed predominantly on unconventional energy particularly with CBM,
CSG and Shale plays helping both emerging and established operators optimise field developments,
explore new areas, enhance and optimise well construction or understand and mitigate risks through the
application of significant lessons learned, solutions, technology and practical know how.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
General Commentary
First Key Step on the Journey to Future Commercialisation
Gold Hydrogen is of the view that the Ramsay Project contains significant prospective resources of both
Natural Hydrogen and Helium, with large scale potential that the Company is aiming to commercialise over
time.
There is very little data available for dedicated Hydrogen wells anywhere in the world due to the lack of
analogue wells. Accordingly, there is inherent uncertainty with regard to the expected outcomes of the
Company’s planned activities. To the Company’s knowledge, the only Natural Hydrogen field currently in
production is located in Mali, West Africa, where Natural Hydrogen production is used to power the small
town of Bourakebougou. It has been reported that the Natural Hydrogen wells in Mali do not have any
decline in production and are continually regenerating and producing at the same rate.7
Helium is extremely valuable and indicatively, longer-term bulk pricing is expected to be up to USD450 per
Mcf (thousand cubic feet).8
Natural Hydrogen has a high energy content, and extracting it even in small quantities may prove
commercial for localised applications. Furthermore, given that Helium was also found within both the
Ramsay 1 and Ramsay 2 wells, being able to extract and process both gases in small quantities may provide
potential short-term commercial and / or proof of concept opportunities to help progress the Ramsay
Project.
Important Risk Commentary
It is important to note that there remain both geological and potential development risks associated with
the Ramsay Project and the Company’s commercial and business objectives. These risks relate to the
presence, recovery and potential volumes of both Hydrogen and Helium, but also due to the location of
the resource within agricultural areas and the proximity to National Parks on both Yorke Peninsula and
Kangaroo Island, requiring significant landholder and community engagement. The worldwide, Federal
and South Australian Government and industry efforts to secure Hydrogen as an alternative energy source
provides confidence that any technical and social concerns may be overcome.
About Gold Hydrogen
Gold Hydrogen is focused on the discovery and development of world class Natural Hydrogen and Helium
gases in a potentially extensive province in South Australia. This region had its Natural Hydrogen and
Helium potential confirmed by the Company via its maiden 2023 / 24 drilling and well testing campaigns.
The domestic and global demand for Hydrogen and Helium, combined with new exploration techniques
and experienced personnel, provides Gold Hydrogen with an extraordinary opportunity to define and
ultimately develop a new Natural Hydrogen and Helium gas province.
7
“Natural Hydrogen: a new source of carbon free and renewable energy that can compete with hydrocarbons”,
First Break Volume 40, October 2022 (available via www.goldhydrogen.com.au/technical-articles/ )
8
February 2024, www.noblehelium.com.au , quoting Kornbluth Consulting.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
The combined permit area of the Gold Hydrogen group is now in excess of 75,000km2
. Gold Hydrogen
holds one granted exploration license (the Ramsay Project - PEL 687) and one application area, whilst its
two 100% owned subsidiary companies (White Hydrogen Australia and Byrock Resources) hold an
additional seven (7) applications for Natural Hydrogen and Helium exploration within South Australia.
Gold Hydrogen is also the preferred applicant for four (4) gas storage exploration licenses applications
(GSELA) covering an area of approximately 8,000km2
within the Yorke Peninsula portion of PEL 687 in
South Australia.
The group’s permit areas are characterised by low population densities, cooperative stakeholders and
aspects of the natural environment suited to the exploration and development of a future Natural
Hydrogen and Helium gas province. Gold Hydrogen places considerable importance on close liaison with
landholders, traditional owners and all other stakeholders, and this approach has led to the grant of its
key tenement PEL 687 in South Australia. The Company intends to continue to invest in these efforts.
Further Information
Further information on the Gold Hydrogen group, its projects, and its Board and Management can be
found on the Company’s website (www.goldhydrogen.com.au). Gold Hydrogen also has accounts on
LinkedIn and Twitter (@GHY_ASX), and copies of market releases will be emailed to all interested parties
who register via investorhub.goldhydrogen.com.au/auth/signup.
This announcement has been authorised for release by the Managing Director.
On behalf of the Board
Karl Schlobohm
Company Secretary
For Company Enquiries Contact:
Neil McDonald – Managing Director Karl Schlobohm – Company Secretary / CFO
nmcdonald@goldHydrogen.com.au kschlobohm@goldHydrogen.com.au
+61 7 3521 8038 +61 7 3521 8038
For Media Enquiries Contact:
Matthew Doman – Crestview Strategy
matthew.doman@crestviewstrategy.com
+61 421 888 858
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
Prospective Resource Statements
The Prospective Resource Statements for Natural Hydrogen and for Helium have been included in this
announcement under the approval of Mr Billy Hadi Subrata, Chief Technical Officer for Gold Hydrogen,
who is a Qualified Petroleum Reserves and Resources Evaluator. Mr Hadi Subrata confirms that, as at the
date of this announcement, there is no change to information or additional information, since the effective
dates, that would materially change the estimates of prospective resources quoted.
Forward Looking Statement / Future Performance
This announcement may contain certain forward-looking statements and opinion Forward-looking
statements, including projections, forecasts and estimates, are provided as a general guide only and should
not be relied on as an indication or guarantee of future performance and involve known and unknown
risks, uncertainties, assumptions, contingencies and other important factors, many of which are outside
the control of the Company and which are subject to change without notice and could cause the actual
results, performance or achievements of the Company to be materially different from the future results,
performance or achievements expressed or implied by such statements. Past performance is not
necessarily a guide to future performance and no representation or warranty is made as to the likelihood
of achievement or reasonableness of any forward-looking statements or other forecast. Nothing contained
in this announcement, nor any information made available to you is, or and shall be relied upon as, a
promise, representation, warranty or guarantee as to the past, present or the future performance of Gold
Hydrogen Limited.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
Table 1: Summary of Ramsay 2 - Stage 1 Testing (released in original form on 27 May 2024)
Name: Ramsay 2
Location (UTM zone 53 GDA2020)
X 747,761.61
Y 6149371.41
Permit PEL687
Entity holders Gold Hydrogen 100%
Zones tested MDT zone, Zone 2 and 3 Zone 4 to 8
Resources Helium Hydrogen
Formation Kulpara Dolomite Kulpara/Parara Limestone
Gross thickness and net pay
thickness
180m Gross 406m Gross
Geological rock type Dolomite Limestone
Depth of the zones tested
612m, 642m, 712m, 754m,
and 777.5mMD
197m, 289m, 346.5m,
385m, and 531mMD
Type of test
Commingled test on zone 2
and 3 for few hours followed
by overnight build up
Pressure test on single
zone for few hours
followed by overnight build
up
Phase recovered Gas/Water Gas/Water
Corrected H2 and He concentration
in gas recovered from downhole
sample
Up to 17.5% He Up to 95.8% H2
Flow rates, choke size, volumes
recovered
TBA in next extended flow test in Q2/Q3 2024
Fracture stimulation None None
Material non hydrocarbons Nitrogen, Hydrogen Nitrogen, Helium
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
Table 2: Ramsay 1 and 2 – Stage 2 well test (released in original form on 2 August 2024 and 17 October 2024)
Name: Ramsay 1 Ramsay 2
Location (UTM zone 53 GDA2020)
X 748,208.07 747,761.61
Y 6149545.7 6149371.41
Permit PEL687 PEL 687
Entity holders Gold Hydrogen 100% Gold Hydrogen 100%
Zones tested Zone 2 and 3 Zone 7 and 8
Resources Helium Hydrogen
Formation Kulpara Dolomite Parara Limestone
Gross thickness and net pay thickness 180m Gross 406m Gross
Geological rock type Dolomite Limestone
Depth of the zones tested 900 mMD 197mMD and 289mMD
Type of test Commingled pressure test Commingled pressure test
Phase recovered Gas/Water Gas/Water
Corrected H2 and He concentration in
gas recovered from downhole sample
36% He Up to 42% (still increasing)*
Flow rates, choke size, volumes
recovered
1 Mscf/day gas constraint by
pump capacity and flow
intermittently with water;
choke size 20/64 inch;
volumes recovered 0.55 MScf
0.5 Mscf/day gas constraint by pump
capacity with continuous flow with
water; choke size 128/64 inch;
volumes recovered 1.02 MScf
Fracture stimulation None None
Material non hydrocarbons Nitrogen, Hydrogen Nitrogen, Helium
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
Table 3: Summary of Helium-4 (4
He) and Helium-3 (3
He) Results (Oxford University) in Ramsay 2
(released in original form on 30 October 2025)
Name: Ramsay 2
Location UTM zone 53 GDA2020
X 747,707.85
Y 6149385.46
Permit PEL687
Entity holders Gold Hydrogen 100%
Zones tested
Zone
1_sample 11
Zone 2-
3_sample
19
Zone
4_sample 32
Zone
5_sample 46
Zone
6_sample 62
Zone
7_sample 79
Resources
Hydrogen-
Helium
Helium Hydrogen Hydrogen Hydrogen Hydrogen
Formation Basement Kulpara Fm Kulpara Fm
Parara
Limestone
Parara
Limestone
Parara
Limestone
Gross thickness
and net pay
thickness
>200m
Gross
180m Gross 155m Gross 406m Gross 406m Gross 406m Gross
Geological rock
type
Basement Dolomite Limestone Limestone Limestone Limestone
Depth of the
zones tested
1002 mMD 712mMD 530 mMD 384 moms 343 mMD 289 mMD
Type of test Noble gas abundance and isotopic quantification
Phase
recovered
Gas Gas Gas Gas Gas Gas
[4
He],
ccSTP/ccSTP
3
He/4
He
R/Ra
3
He ppt
1.44E-07
3.23E-07
0.23
0.05
6.52E-04
9.26E-09
0.0066
6.04
4.21E-08
1.72E-06
1.2306
0.07
5.54E-07
6.84E-08
0.0489
0.04
3.05E-08
1.55E-06
1.11
0.05
1.59E-07
7.57E-07
0.5408
0.12
Flow rates,
choke size,
volumes
recovered
N-A. Laboratory test of discrete samples
Fracture
stimulation
None None None None None None
Material non-
hydrocarbons
N2, H2, He,
CO2
N2, H2, He,
CO2
N2, H2, He,
CO2
N2, H2, He,
CO2
N2, H2, CO,
CO2
N2, H2, He,
CO2
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
Table 4: Summary Table of Helium-4 (4
He) and Helium-3 (3
He) results (Oxford University) in Ramsay 1
(released in original form on 30 October 2025)
Name: Ramsay 1
Location UTM zone 53 GDA2020
X 748,208.07
Y 6149545.7
Permit PEL687
Entity holders Gold Hydrogen 100%
Zones tested Zone 1_sample 8
Zone 2-3_sample
109451
Zone 2-3_sample
109477
Resources Hydrogen-Helium Helium Helium
Formation Basement Kulpara Fm Kulpara Fm
Gross
thickness and
net pay
thickness
>200m Gross 180m Gross 180m Gross
Geological
rock type
Basement Dolomite Dolomite
Depth of the
zones tested
970 mMD 900 mMD 900 mMD
Type of test Noble gas abundance and isotopic quantification
Phase
recovered
Gas Gas Gas
[4
He],
ccSTP/ccSTP
3
He/4
He
R/Ra
3
He ppt
3.42E-04
9.65E-09
0.0069
3.30
5.34E-02
9.31E-09
0.0067
497.39
9.59E-02
9.39E-09
0.0067
900.51
Flow rates,
choke size,
volumes
recovered
N-A. Laboratory test of discrete samples
Fracture
stimulation
None None None
Material non-
hydrocarbons
N2, H2, He, CO2 N2, H2, He, CO2 N2, H2, He, CO2
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899
Table 5: Prospective Resource Statement for Natural Hydrogen
Gold Hydrogen’s Ramsay Project: Prospective Resources* of Hydrogen in ‘000 Tonnes – 30 Sept
2021
PEL Prospects
SPE
PRMS
Sub-
class
1U
Low
Estimate
2U
Best
Estimate
Mean
3U
High
Estimate
Pg Pd Pc
PEL 687
All
Prospects
and Leads
207 1,313 4,187 8,820 22% 48% 10%
Yorke
Peninsula
PEL 687 Ramsay FB Prospect 124 931