Potential to Accelerate Helium Development at Ramsay
Supported by World-Leading Purity Results, Independent
Commercial Modelling and Amid Tightening Global Supply
Highlights
Based on the extensive work completed by Gold Hydrogen (set out below), the Company
is progressing commercialisation studies across multiple pathways, including green
methanol, power generation, and fuel cell applications for Natural Hydrogen, as well as
bottled industrial / commercial-grade Helium production.
• The Ramsay Project has delivered multiple high-value datasets, including:
o 2023 airborne survey,
o 2023 fluid inclusion study,
o 2024 seismic survey, and
o ongoing drilling and well-testing results, supplemented by extensive historical
data.
Independent consultants have also completed separate Prospective Resource estimates
for Hydrogen and Helium across the Ramsay Project area (refer Tables 1 and 2 appended).
Drilling and well-testing to date have confirmed exceptional gas purities, with Natural
Hydrogen up to 97% and Helium up to 36.9% (both air-corrected). Helium-3 has also been
detected in samples analysed by international laboratories. Based on published
information available, the Company considers these results to be world-leading.Ref 1
Worley Consulting (Worley) has completed an independent high-level commercial
assessment of three indicative Helium production scenarios, based on inputs provided by
the Company, for its 100%-owned Ramsay Project on the Yorke Peninsula, South
Australia.Ref 2
Modelling undertaken by Worley indicates that, based on the inputs provided by the
Company, Ramsay may have the potential to be commercially viable with as few as two
wells, assuming sustained Helium flow rates of ~29 thousand standard cubic feet (Mscf)
per day per well. Scaling to ten wells is indicated by Worley to improve the NPV, IRR and
payback for a gaseous product.
Quantum Technology Corp (Canada), a specialist in modular, skid-mounted Helium and
Hydrogen purification plants, with operating facilities across North America and Europe
(via Cryo Diffusion SAS, France), has provided access to commercial-scale pilot plants.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 2
While continuing to advance its medium- to long-term Natural Hydrogen opportunities,
the Company has identified the potential for an accelerated Helium development at
Ramsay. The Worley assessment provides preliminary inputs into evaluating this option.
The Company will continue working with Worley to refine these models in parallel with
the next flow-testing campaign, currently expected to commence in June 2026.
Subject to flow-testing outcomes and potential contingent resource definition, Gold
Hydrogen intends to progress an accelerated FEED process, positioning a Helium-focused
development at Ramsay as the initial commercial platform for longer-term Natural
Hydrogen and Helium exploitation.
Australia and New Zealand currently import 100% of their Helium, following the closure
of the Darwin LNG Helium plant in late 2023. Helium is a high-value, non-manufacturable
commodity, with structurally rising demand driven by advanced industrial and
technological applications.Ref 3
Recent disruption at Qatar’s Ras Laffan facility has temporarily removed an estimated 30–
35% of global Helium supply for an expected 12–18 months, coinciding with accelerating
demand from AI, data centres, semiconductors, MRI and defence sectors.Ref 4
Comments from the Chairman
Gold Hydrogen Chairman, the Hon. Alexander Downer AC, said:
“Helium currently sits on Australia’s Strategic Materials List, but that is a holding pattern, and the
events of recent weeks have laid bare just how exposed Australia is. We import 100% of a gas that is
essential to chips, MRI, defence and AI infrastructure, and the global supply chain recently lost roughly
a third of its production overnight. It is time to move Helium from the Strategic Materials List back onto
Australia’s Critical Minerals List, where it belongs.
“Independent commentary, including a recent piece by the Australian Strategic Policy Institute, has put
the issue plainly: no Helium, no chips.Ref 5
Gold Hydrogen has a unique opportunity, and a responsibility,
to help Australia rebuild a sovereign Helium capability and to be part of the solution for our allies and
trading partners.”
Comments from the Managing Director
Gold Hydrogen Managing Director, Neil McDonald, said:
“With Helium recorded across our Ramsay Project with air-corrected purities of up to 36.9%, against a
typical commercial cut-off of 0.3% (albeit as a by-product), and with global supply under unprecedented
pressure, Gold Hydrogen sees a strong case for moving quickly to capitalise on the opportunity for
domestic Helium production in Australia. We are excited at the potential for accelerating a Helium
development at Ramsay; working with Worley on commercial modelling parameters, aiming to move
towards production wells off the back of a successful flow testing program, and ultimately re-
establishing Australia’s domestic production and supply of Helium.”
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 3
Comments from Worley
Jessica Dwyer, Director Chemicals, Fuels and Low Carbon APAC at Worley Consulting, said:
“Worley is pleased to be working with Gold Hydrogen on the Ramsay Project. Our initial high-
level commercial assessment indicates that, on the inputs provided by the Company, the project has
the potential to be commercially viable under the modelled scenarios. We look forward to progressing
an accelerated Front End Engineering Design with Gold Hydrogen following the upcoming flow testing
program, with the objective of continuing to advance the case for Australian Helium production.”
Comments from Quantum Technology Corp.
Calvin Winter, President said:
“Quantum Technology Corp. is pleased to be working with Gold Hydrogen in providing proven cost
effective modular Helium and Natural Hydrogen purification skids to transform raw well gas to high
pressure pure Helium gas and / or Natural Hydrogen gas at commercial purities.”
Further Details
The Board of Director of Gold Hydrogen Limited (ASX: GHY) is pleased to provide an update in relation
to its future potential commercialisation pathways, including an independent high-level commercial
assessment of three potential Helium production scenarios for its Ramsay Project undertaken by
Worley, based on the inputs provided by the Company.Ref 2
Gold Hydrogen’s Ramsay Project
Since the Company’s successful IPO in January 2023, numerous workstreams have been undertaken
as part of its ongoing exploration and appraisal efforts to determine the prospectivity of, and future
potential commercial pathways for, the Natural Hydrogen and Helium gases available at its flagship
Ramsay Project in South Australia.
The key workstreams and studies undertaken by Gold Hydrogen to date include:
static and dynamic sub-surface modelling;
a 10,529 line kilometre airborne survey, and its subsequent interpretation;
reservoir rock characterization studies to determine permeability, porosity, etc;
a 575km 2D seismic survey;
soil gas sampling programs;
drilling the Company’s first four (4) wells with associated image and magnetic resonance logging,
gas sampling and laboratory analysis;
exploration well testing of the Ramsay 1 and Ramsay 2, together with gas sampling analysis from
Australian and international laboratories;
fluid-inclusion studies to determine the existence of Natural Hydrogen and / or Helium across the
broader Ramsay project area as well as the Company’s regional application areas.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 4
In addition, independent consultants have provided the Company with separate Prospective Resource
estimates for both Hydrogen and Helium within the Ramsay Project area, as outlined in Table 1 and
Table 2 appended.
On the basis of the various data streams available to the Company as a result of the above activities, it
is confident in the existence of both Natural Hydrogen and Helium across the broader Ramsay Project
footprint. Further work must be undertaken to confirm the Company’s ability to viably access and
bring these gases to surface in sufficient quantities to support future the commercial development of
the Project. This will be one of the key objectives of the Company’s upcoming flow testing campaign.
Potential Future Commercialisation Pathways
As previously disclosed, Gold Hydrogen continues to engage with a range of domestic and international
parties in relation to its aspirations to commercialise the Ramsay Project. These discussions have
produced a number of potential future commercialisation pathways, contingent on the success of the
upcoming well testing campaign.
Some of the potential commercialisation pathways currently under consideration include the
following:
Potential Natural Hydrogen Pathways
Two Natural Hydrogen commercial pilot-level pathways are being considered in parallel, sequenced so
that the first pathway would directly support the potential for Helium production, and the second
potentially scaling into Liquid Natural Hydrogen export and Green Methanol over time. Quantum
Technology Corp of Canada has confirmed it can supply modular Natural Hydrogen purification
equipment, in addition to the Helium plant discussed under Helium Pathway 2.
Natural Hydrogen Pilot 1 — Natural Hydrogen to Energy for Helium Production
This pilot is currently being scoped, and would deploy a Hydrogen Fuel Cell on site at Ramsay,
converting Natural Hydrogen produced from the well stream into electricity, to power a modular
Helium purification plant. If this pathway is pursued, it would be intended to be operational alongside
the Project’s first Helium production (see below). Beyond its direct role powering the Helium plant,
the pilot would establish an integrated Natural Hydrogen-to-electrons reference installation for
off-grid power applications in remote Australia.
Natural Hydrogen Pilot 2 — Natural Hydrogen to Compressed Gas, Scaling to Liquid Natural Hydrogen
and Green Methanol
In parallel, the Company is progressing a compressed gaseous Natural Hydrogen pilot pathway,
comprising a modular Quantum Technology QPure-H₂ purification plant feeding fuel-cell-grade
Hydrogen into 350-bar tube trailers for a potential Hydrogen trucking trial with a major international
automotive partner. This pilot would be positioned as a direct sovereign substitute for imported diesel
on one of Australia’s highest-volume freight corridors. Subject to the performance of this pilot project
and offtake demand, the Company aspires to a scale-up pathway into two longer-dated streams: (i)
grid-scale liquefaction for Liquid Natural Hydrogen export to Japan, under discussion with established
Japanese industrial partners; and (ii) a Green Methanol stream, currently under a feasibility
assessment discussion with a major international chemicals partner for a potential facility on the Yorke
Peninsula.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 5
Potential Helium Pathways
Helium Pathway 1 — Scaled Helium Development
This pathway involves the consideration of a scaled gaseous and/or liquid Helium development on the
Yorke Peninsula. As described further in the Worley section below, Worley’s indicative modelling
considered scenarios ranging from two (2) wells up to a ten (10) well gaseous project, and up to twenty
(20) wells for a full commercial development. The Company’s objective under this pathway is to work
with Worley on an accelerated FEED process, with well count, plant capacity, product form (gaseous
versus liquid Helium) and phasing to be optimised against the actual upcoming Ramsay flow testing
outcomes. This pathway is positioned for the potential of a larger scale, longer-dated development
optionality for Helium at Ramsay.
Helium Pathway 2 — Quantum Technology Commercial Helium Pilot
In parallel, the Company has received a preliminary budget proposal from Quantum Technology for a
modular, skid-mounted Helium purification plant designed to be potentially matched to the best one
to two (1–2) wells from the upcoming Ramsay flow testing program. Quantum Technology is an
experienced supplier of modular Helium plants, with reference facilities in North America, and a
product range covering single-well and multi-well configurations. The Quantum pilot would be
positioned as a smaller-scale, lower capital, faster-to-market option that could potentially deliver first
commercial Helium production from Ramsay, with the aim of re-establishing domestic Helium supply
to the Australian market.
The Quantum pilot would also be expected to provide valuable operating data — on sustained well
deliverability, recovery rate, plant performance and product quality — that would directly inform and
de-risk the larger development (Helium Pathway 1). The two potential pathways are therefore
complementary rather than alternative: a near-term Quantum pilot to generate first cash flow and
field data, with the subsequent option to scale-up via Helium Pathway 1 as the Company’s resource
base and the offtake market both mature over time.
Both pathways remain subject to the successful completion of the Ramsay flow testing program,
regulatory approvals, completion of FEED, the definition of a Contingent Resource, the negotiation of
offtake arrangements, and a final investment decision by the Board. The Company will provide further
updates to the market in due course.
Worley Helium Study
The Company has previously disclosed the fact that it has been working with Worley in relation to
potential commercial production modelling scenarios for Helium. The high-level assessment
undertaken by Worley, based on the inputs provided by the Company, to date has provided a high-
level technical definition of the production plant, order-of-magnitude capital cost estimates, and
commercial modelling of NPV, IRR and payback period for both gaseous and liquid Helium product
cases.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 6
Importantly, the scenarios assessed by Worley are indicative modelled cases based on typical process
arrangements, typical recoveries and well stream conditions provided by the Company. However, they
are not based on a defined resource, and in accordance with ASIC and ASX guidance, the Company
cannot currently make any specific disclosures associated with any of the preliminary project
economics.
The modelled scenarios ranging from two (2) wells up to a ten (10) well gaseous project indicate
Ramsay has the potential to be commercially viable if they can sustain a Helium flow rate of 29
thousand standard cubic feet (Mscf) per day each.
This modelling will be specifically refined post completion of the upcoming Ramsay flow testing
program and any subsequent definition of a Contingent Resource for Helium. As part of concept
developments and undertaking a commercial assessment, the Worley modelling demonstrates the
potential for the commercial extraction of Helium at the Ramsay Project using currently available
technology. This assessment therefore assists Gold Hydrogen with the opportunity to book a
Contingent Resource on the back of successful flow testing results from its upcoming campaign.
World-Leading Helium Purity
Gold Hydrogen has previously confirmed Helium samples from the Ramsay Project at air-corrected
purities of up to 36.9%.Ref 1
This is significantly above the 0.3% cut off rate that is generally applied to
Helium extraction within Natural Gas Fields. Independent validation by Oxford University has also
confirmed the presence of Helium-3 at concentrations of up to 901 ppt. The Company believes its
results to be amongst the highest in the world, based on published information available.Ref 1
A Tightening Global Helium Market
Helium is a non-substitutable strategic gas underpinning semiconductor manufacturing (including
extreme ultraviolet lithography), AI infrastructure and data centres, MRI and other medical imaging,
aerospace, defence systems, quantum computing and cryogenics.
Australia and New Zealand currently produce no Helium domestically and rely entirely on imports. The
closure of the Darwin LNG Helium plant at the end of 2023 left the region with no sovereign Helium
supply.Ref 3
Domestic demand from AI, data centres, MRI, medical and defence applications was already growing
strongly prior to recent supply disruption. Strikes affecting Qatar’s Ras Laffan complex have now
removed an estimated 30–35% of global traded Helium supply for an expected 12–18 months.Ref 4
Qatar and the United States together supply close to 90% of the global market, and it has been
reported that there is no readily available substitute source at this scale.Ref 5
Significant Interest in GHY Helium
Gold Hydrogen is currently fielding a number of enquiries from interested parties encompassing
Helium offtake, Helium plant vendors, potential investors, and the Australian Federal Government.
Whilst there are a number of Helium exploration projects in Australia, Gold Hydrogen is the only known
project with multiple wells, proven Helium occurrences and upcoming flow testing occurring in mid-
2026.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 7
Next Steps
1. Completion of the Ramsay well testing program, with site equipment currently schedule to
mobilise in late May 2026.
2. If the Company’s upcoming flow testing campaign is successful, refinement of the Worley
commercial scenarios using actual flow test results, and a defined contingent resource for Helium.
3. Selection of Helium production plant capacity, product type (gaseous vs liquid) and phasing.
4. Commencement of an accelerated pre-FEED / FEED process with Worley to support a final
investment decision.
5. Continued engagement with strategic partners, landowners, the South Australian Government and
Indo-Pacific allies.
Important Notices and Disclaimers
Hypothetical scenarios. The high-level commercial scenarios prepared by Worley and referenced in
this announcement are hypothetical, using high-level technical definition, prepared on the basis of
typical process arrangements, typical recoveries, inputs provided by Gold Hydrogen including well
drilling and completion costs, well stream conditions and forecast Helium market pricing. They do not
constitute a feasibility study, a reserve or resource estimate, or a forecast of project economics. The
scenarios will be refined following completion of the upcoming flow testing program and any
subsequent definition of a contingent resource.
No resource estimate. No SPE-compliant reserves or resources are reported in this announcement.
Hence the Company cannot publish any modelled production rates, well counts, capital costs, NPV, IRR
and payback figures at this time.
Forward-looking statements. This announcement contains forward-looking statements regarding the
Company’s aspirational plans and intentions. Such statements are subject to known and unknown risks
and uncertainties, and actual results may differ materially. Gold Hydrogen does not undertake to
update any forward-looking statements except as required by law.
Important Risk Commentary
It is important to note that there remain both geological and potential development risks associated
with the Ramsay Project and the Company’s commercial and business objectives. These risks relate to
the presence, recovery and potential volumes of both Natural Hydrogen and Helium, but also due to
the location of the gas systems within agricultural areas and the proximity to National Parks on both
Yorke Peninsula and Kangaroo Island, requiring significant landholder and community engagement.
The worldwide, Federal and South Australian Government and industry efforts to secure Hydrogen as
an alternative energy source provides confidence that any technical and social concerns may be
overcome.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 8
About Gold Hydrogen
Gold Hydrogen is focused on the discovery and development of world class Natural Hydrogen and
Helium gases in a potentially extensive province in South Australia. This region had its Natural
Hydrogen and Helium potential confirmed by the Company via its maiden 2023 / 24 drilling and well
testing campaigns.
The domestic and global demand for Hydrogen and Helium, combined with new exploration
techniques and experienced personnel, provides Gold Hydrogen with an extraordinary opportunity to
define and ultimately develop a new Natural Hydrogen and Helium gas province.
The combined Natural Hydrogen permit area of the Gold Hydrogen group is in excess of 75,000km2
.
Gold Hydrogen holds one granted petroleum exploration license (the Ramsay Project - PEL 687) and
an exclusive application area (PELA 792). In addition, its two 100% owned subsidiary companies (White
Hydrogen Australia and Byrock Resources) hold an additional seven (7) exclusive application areas for
Natural Hydrogen and Helium exploration within South Australia.
Gold Hydrogen is also the preferred applicant for four (4) gas storage exploration licenses applications
(GSELA) covering an area of 8,107km2
within the Yorke Peninsula portion of PEL 687 in South Australia.
These storage licence applications are in addition to the granted exploration licence and application
licences. A 100% owned Gold Hydrogen subsidiary, Sustainable Minerals Group Pty Ltd, also holds a
mineral lease on the Yorke Peninsula potentially prospective for iron-oxide, copper and / or gold
mineralisation.
The group’s permit areas are characterised by low population densities, cooperative stakeholders and
aspects of the natural environment suited to the exploration and development of a future Natural
Hydrogen gas province. Gold Hydrogen places considerable importance on close liaison with
landholders, traditional owners and all other stakeholders, and this approach has led to the grant of
its key tenement PEL 687 in South Australia. The Company intends to continue to invest in these
efforts.
This announcement has been authorised for release by the Board of Directors.
On behalf of the Board
Karl Schlobohm
Company Secretary
For Company Enquiries Contact:
Neil McDonald – Managing Director Karl Schlobohm – Company Secretary / CFO
nmcdonald@goldhydrogen.com.au kschlobohm@goldhydrogen.com.au
+61 7 3521 8038 +61 7 3521 8038
For Media Enquiries Contact:
Matthew Doman – Crestview Strategy
matthew.doman@crestviewsrtrategy.com
+61 421 888 858
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 9
Release References
1. (a) ASX announcement of 17 October 2024 ‘Ramsay Project – Helium Testing Update’ (Helium
recorded at the wellhead at air-corrected purities of up to 36.9%). Refer Table 3 appended for
technical details.
(b) ASX announcement of 2 December 2025 ‘Ramsay 3 Drilling Successfully Completed – World
Class Elevated Levels of Natural Hydrogen Confirmed up to 97% Purity’ (air corrected). Refer
Tables 4A and 4B appended for technical details.
(c) ASX announcement of 30 October 2024 ‘Helium-3 Confirmed at Ramsay Project’, (including
independent isotopic analysis by the University of Oxford with Helium-3 concentrations up to 901
ppt). Refer Table 5 appended for technical details.
2. Worley Consulting, ‘Natural Helium Commercial Scenarios Summary Report’, 411010-01261-PM-
REP-0001, Rev 0.
3. Gasworld, ‘Australia ceases helium production as its sole plant shuts down’, December 2023; Bayu-
Undan to Darwin Pipeline / Darwin LNG, final cargo loaded 11 November 2023. The BOC Darwin
helium plant was the only helium production facility in the Southern Hemisphere and supplied
approximately 3% of global helium prior to closure.
4. Chemical & Engineering News (C&EN), ‘Iran war threatens global helium supply’, March 2026;
Fortune, ‘Iran war cuts off helium from Qatar’, 21 March 2026; Reuters / CNBC, March 2026. Qatar
Energy halted production at Ras Laffan Industrial City on 2 March 2026 and declared force majeure
on 4 March 2026 following Iranian drone and missile strikes; further strikes on 18–19 March 2026
caused “extensive damage” to the Pearl GTL facility and additional LNG infrastructure. Industry
analysts (including Kornbluth Helium Consulting and Exiger) estimate that approximately one-third
of global helium supply has been removed from the market, with restart timelines measured in
months to years and helium spot prices having doubled since the crisis began.
5. Arup George, ‘No helium, no chips: why Australia needs to make the gas again’, The Strategist,
Australian Strategic Policy Institute, 1 April 2026. The article notes that Qatar and the United States
together supply close to 90% of global helium, that Australia removed helium from its Critical
Minerals List in December 2023, and that Australia’s only helium production facility (the Darwin
LNG plant) shut down the same year.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 10
Table 1 – Prospective Resource Statement for Natural Hydrogen
Gold Hydrogen’s Ramsay Project: Prospective Resources* of Hydrogen in ‘000 Tonnes – 30 Sept
2021
PEL Prospects
SPE
PRMS
Sub-
class
1U
Low
Estimat
e
2U
Best
Estimat
e
Mean
3U
High
Estimat
e
Pg Pd Pc
PEL 687
All
Prospects
and Leads
207 1,313 4,187 8,820
22
%
48
%
10
%
Yorke
Peninsul
a
PEL 687 Ramsay FB
Prospec
t
124 931 2,712 6,989
22
%
50
%
11
%
PEL 687 Ramsay Lst
Prospec
t
10 70 191 492
26
%
50
%
13
%
PEL 687 Maitland Lead 7 26 40 92
17
%
35
%
6%
Kangaro
o Island
PEL 687 Navigator Lead 34 152 280 678
19
%
40
%
8%
PEL 687
Kanmanto
o
Prospec
t
32 134 237 569
25
%
40
%
10
%
* This estimate of Natural Hydrogen Prospective Resources must be read in conjunction with the
notes below, and it should be noted that the estimated quantities of Natural Hydrogen that may
potentially be recovered by the application of a future development project(s) relate to
undiscovered accumulations. These estimates have both an associated risk of discovery and a risk of
development. Further exploration, appraisal and evaluation is required to determine the existence
of a significant quantity of potentially recoverable Natural Hydrogen.
Notes:
1. This reserves statement presents Gold Hydrogen’s Prospective Resources. Gold Hydrogen
currently has no Reserves and no Contingent Resources.
2. Estimates are assessed to comply with the ASX Listing Rules for Prospective Resources and SPE-
PRMS 2018 with the understanding that naturally occurring Hydrogen may be considered a
hydrocarbon since it has energy content and can be used stand alone and/or blended with sales
gas. “U” implies Prospective Resources.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 11
3. Per ASX Listing Rules 5.28.4 and 5.28.5 estimates are unrisked and aggregated arithmetically by
category, hence caution that the aggregate low estimate may be a very conservative estimate and
the aggregate high estimate may be a very optimistic estimate due to the portfolio effects of
arithmetic summation.
4. Probabilistic methods are used to prepare the estimates. The distribution of the estimates is the
“full distribution” and has not been truncated by application of the MEPS (minimum economic
pool size concept).
5. The Reference Point is at the wellhead/edge of lease (i.e. wellhead facilities) so the estimates have
no deduction for flare, vent or fuel consumed in operations.
6. Pg (Chance of Geologic Discovery), Pd (Chance of Development) and Pc (Chance of Commerciality
= Pg x Pd) are calculated as a weight average of the P50’s of the H2 (‘000 Tonnes) of the prospects.
7. Pg incorporates Play Risk and Prospect Risk.
8. Pd incorporates an assessment across all SPE-PRMS Commerciality Criteria (i.e. not just
economics).
9. Information in the table is rounded. Some totals in the tables may not add due to rounding.
10. This reserves statement:
a. is based on, and fairly represents, information and supporting documentation prepared by
the qualified petroleum reserves and resources evaluators listed in note 14 below. Details of
each qualified petroleum reserves and resources evaluator’s employment and professional
organisation membership are set out in note 14 below;
b. has been approved by Luke Titus, who is a qualified petroleum reserves and resources
evaluator and whose employment and professional organisation membership details are set
out in note 14 of this reserves statement;
c. is issued with the prior written consent of Luke Titus and Teof Rodrigues & Associates (“TRA”
- involving Teof Rodrigues, Paul Strong, and Greg Horton, whose employment and
professional organisation membership details are set out in note 14 of this reserves
statement) as to the form and context in which the estimated Natural Hydrogen resources
and the supporting information are presented.
11. There is no change to information or additional information, since the effective date of 30
September 2021, that Gold Hydrogen and TRA are aware of that would materially change the
estimates in this reserves statement.
12. Gold Hydrogen engages independent experts TRA to evaluate reserves
Share your feedback
Discover