Non Deal Roadshow Presentation
Released
Released
Announcement PDF
1
Gold Hydrogen Limited
1
Committed to Developing Naturally
Occurring Hydrogen and Helium in
Australia
Committed to Developing Naturally Occurring
Hydrogen and Helium in Australia
Non-Deal Roadshow
Neil McDonald – Managing Director
2
Gold Hydrogen Limited
Important Notice & Disclaimer
This presentation is not a prospectus, disclosure document or offering document under Australian law or under any other law.
It is for informational purposes only. This document does not constitute, and should not be construed as, an offer to issue or
sell or a solicitation of an offer or invitation to subscribe for, buy or sell securities in Gold Hydrogen Limited ABN 74 647 468 899
(Gold Hydrogen).
Any material used in this presentation is only an overview and summary of certain data selected by the management of Gold
Hydrogen. The presentation does not purport to contain all the information that a prospective investor may require in
evaluating a possible investment in Gold Hydrogen nor does it contain all the information which would be required in a
disclosure document prepared in accordance with the requirements of the Corporations Act and should not be used in isolation
as a basis to invest in Gold Hydrogen. The information contained in this presentation is not investment or financial product
advice and has been prepared as general information only, without consideration for your particular investment objectives,
financial situation or particular needs. Recipients of this presentation must make their own independent investigations,
consideration, and evaluation of Gold Hydrogen. Gold Hydrogen recommends that potential investors consult their
professional advisor/s as an investment in Gold Hydrogen is considered to be speculative in nature.
Statements in this presentation are made only as of the date of this presentation unless otherwise stated and the information
in this presentation remains subject to change without notice. Reliance should not be placed on information or opinions
contained in this presentation.
To the maximum extent permitted by law, Gold Hydrogen disclaims any responsibility to inform any recipient of this
presentation on any matter that subsequently comes to its notice which may affect any of the information contained in this
document and presentation and undertakes no obligation to provide any additional or updated information whether as a result
of new information, future events or results or otherwise.
To the maximum extent permitted by law, no representation or warranty, express or implied, is made as to the fairness,
accuracy, completeness or correctness of the information, opinions or conclusions contained in or derived from this
presentation or any omission from this presentation or of any other written or oral information or opinions provided now or in
the future to any person.
To the maximum extent permitted by law, neither Gold Hydrogen nor, any affiliates, related bodies corporate and their
respective officers, directors, employees, advisors and agents (Relevant Parties), nor any other person, accepts any liability as to
or in relation to the accuracy or completeness of the information, statements, opinions or matters (express or implied) arising
out of, contained in or derived from this presentation or any omission from this presentation or of any other written or oral
information or opinions provided now or in the future to any person.
This presentation includes information regarding the past performance of Gold Hydrogen. Recipients of this presentation
should be aware that past performance should not be relied upon as being indicative of future performance.
This presentation contains statistics, data and other information pertaining to Gold Hydrogen’s business and operations.
Recipients of this presentation should note that industry and market data and statistics are
inherently predictive and subject to uncertainty and not necessarily reflective of actual industry or market conditions. There is
no assurance that any of the estimates or projections in this presentation will be achieved. Gold Hydrogen has not
independently verified, and cannot give any assurances to the accuracy or completeness of, this market and industry data or
the underlying assumptions used in generating this market and industry data.
This presentation contains “forward looking statements” concerning the financial condition, results of operations and business
of Gold Hydrogen. All statements other than statements of fact or aspirational statements, are or may be deemed to be
“forward looking statements”. Often, but not always, forward looking statements can generally be identified by the use of
forward looking words such as “may”, “will”, “expect”, “intend”, “plan”, “estimate”, “anticipate”, “continue”, “outlook”, and
“guidance”, or other similar words and may include, without limitation, statements regarding plans, strategies and objectives of
management, future or anticipated production or construction commencement dates and expected costs, resources or
reserves, exploration results or production outputs. Forward looking statements are statements of future expectations that are
based on management’s current expectations and assumptions and known and unknown risks and uncertainties that could
cause the actual results, performance, or events to differ materially from those expressed or implied in these statements. These
risks include, but are not limited to price fluctuations, actual demand, currency fluctuations, drilling and production results,
commercialization, reserve estimates, loss of market, industry competition, environmental risks, physical risks, legislative, fiscal,
and regulatory developments, economic and financial market conditions in various countries and regions, political risks, project
delay or advancement, approvals, and cost estimates. More detail on the risks relevant to Gold Hydrogen’s business and
operations is set out in Risks section of this presentation.
Prospective Resource Statements
The Prospective Resource Statements for Natural Hydrogen and for Helium have been included in presentation under the
approval of Mr Billy Hadi Subrata, Chief Engineer for Gold Hydrogen, who is a Qualified Petroleum Reserves and Resources
Evaluator. Mr Hadi Subrata confirms that, as at the date of this announcement, there are no changes to information or
additional information, since the effective dates, that would materially change the estimates of prospective resources quoted.
QPRRE Statement – Natural Hydrogen
The Prospective Resource Statement for Natural Hydrogen in this presentation is based on, and fairly represents, information
and supporting documentation prepared by independent consultants “Teof Rodrigues & Associates” with an effective date of
30 September 2021, and which forms part of the Company’s Replacement Prospectus dated 29 November 2022. The
Prospective Resource Statement, together with all relevant notes, also appears in the Company’s ASX release of 13 January
2023.
QPRRE Statement - Helium
The Prospective Resource Statement for Helium in this announcement is based on, and fairly represents, information and
supporting documentation prepared by independent consultants “Teof Rodrigues & Associates” with an effective date of 21
February 2024 and 30 October 2024, and which was announced by the Company on those dates together with the
accompanying assumptions and notes.
goldhydrogen.com.au | ASX:GHY |
3
Gold Hydrogen Limited
Table of Contents
Corporate Snapshot & Project Overview
1. Industry Overview
2. What We Have Achieved and Learned
3. Objectives and Executing on Lessons Learned
4. Upcoming Work Program
4
Gold Hydrogen Limited
Gold Hydrogen – Corporate Snapshot
Alexander Downer – Non-Executive Chair
Katherine Barnet – Non-Executive Director
Neil McDonald – Managing Director
Roger Cressey – Executive Director
Board of Directors
1 granted Petroleum Licence – PEL 687 Ramsay Project
8 Petroleum Licence Application Areas
1 granted Mineral Exploration Licence
4 Storage Licence Applications – PEL 687 Ramsay Project
Tenure
Market Cap – $100 million (at $0.55 per share)
Cash on Hand – $22 million
Shares on Issue – 180.5 million
goldhydrogen.com.au | ASX:GHY |
5
Gold Hydrogen Limited
Executive Summary – Natural Hydrogen and Helium
Ramsay Project 100%
owned
7,820 km2
plus a further 69,472km2 under
exclusive application
Title over certified
Prospective Resources
1.3 billion kg of natural Hydrogen1
41 Bcf of Helium1
(with a mean of 96 Bcf)
High purity gas sample
levels2
95.8% Hydrogen
Up to 36.9% Helium
Helium-3 detected in samples
1. Prospective Resources are based on un-risked Best Estimate. Refer Appendix for full details.
2. Laboratory gas sample analyses - air (and nitrogen) corrected. Refer ASX releases of 27 May 2024, 2 August 2024 and 17 & 30 October 2024. Technical Tables appended.
Engagements to date with
leading global experts and
contractors
CSIRO, Schlumberger, Total Seismic,
Xcalibur, Savanna Energy Services,
Terrex Seismic, SGS
Commercial and
environmental competitive
advantages
Natural hydrogen provides cost and
emission advantages over other
production sources
A number of global gas projects are
commercial with much lower
concentration
of helium
(<1% helium as a by-product)
goldhydrogen.com.au | ASX:GHY |
6
Gold Hydrogen Limited
Gold Hydrogen project overview
goldhydrogen.com.au | ASX:GHY |
• Gold Hydrogen drilled two exploration wells in 2023, which were subsequently tested in 2024 to validate the
historic 1931 Ramsay Oil Bore site and confirm the presence of high-purity Natural Hydrogen and Helium at
that location.
• The two exploration wells (Ramsay 1 & Ramsay 2) were drilled using narrow-gauge techniques. These wells
were designed for early-stage exploration purposes at low cost to determine the presence of H2 and He. The
program successfully identified the presence of Natural Hydrogen and Helium.
• In mid 2024, an extensive 2D seismic program was undertaken, confirming multiple further drill targets in more
optimal locations than the 1931 and 2023 drill holes.
• Strategic Investment: Following extensive due diligence, site visits and negotiations, Toyota Motor Corporation,
Mitsubishi Gas Chemical Inc and ENEOS Xplora Inc invested $14.5m into Gold Hydrogen in July 2025.
• The forthcoming 2-3 well drilling program has been designed with:
enhanced well engineering to enable a more accurate appraisal of the Ramsay Project’s commercial
potential;
the selection of optimal well locations; and
further de-risked permitting and operational planning.
• Based on the knowledge and results achieved to date, and working with its strategic investors, Gold Hydrogen is
analysing potential commercial opportunities for both Natural Hydrogen and Helium.
7
Gold Hydrogen Limited
1. Industry Overview
8
Gold Hydrogen Limited
Naturally occurring Hydrogen offers significant cost and / or carbon advantages relative to other Hydrogen production
(manufacturing) processes
Gold Hydrogen is exploring for ‘gold’ or
‘white’ (natural) Hydrogen
1(i) Natural Hydrogen is the most cost-effective source of hydrogen
Gold / White
(natural)
Grey Black/Brown Blue Green
Energy source Natural hydrogen Natural gas Coal
Natural gas /
coal
Renewables /
biomass
Environmental impact Low High Very High Low Low
No thermal process
Production cost (A$/kg)1,2 $1.00 $5.60 $6.20-$6.40 $10.20-$10.30
P: $6.40-$25.50
A: $4.70-$23.20
Cost comparable to existing
power generation3
Today, ~95% of all hydrogen produced is
from natural gas
Source: Frost and Sullivan, Sep-2022 (Refer Gold Hydrogen Replacement Prospectus dated 29 November 2022)
1. Source: Christophe Rigollet1, Alain Prinzhofer2,3, Natural Hydrogen: A New Source of Carbon-Free and Renewable Energy That Can Compete With Hydrocarbons, First Break, Volume 40, Issue 10, Oct 2022, p. 78 – 84
DOI: https://doi.org/10.3997/1365-2397.fb2022087; “The Bourakébougou field, in Mali, represents the first natural hydrogen deposit studied both scientifically and industrially.
It gives us information on its renewability, on the natural flows involved and therefore on its sustainable exploitation. It is possible to estimate that the cost of operating hydrogen would be less than $1/kg, which is significantly cheaper than
any manufactured hydrogen, whether green, grey, or blue. Equivalent work is in progress in other continents, in order to be able to compare our knowledge of this Malian field with other fields in the world, which will make it possible to
better ensure the industrial and societal interest of R&D for this new field.”
2. P = Polymer electrolyte membrane electrolysis. A = Alkaline Electrolysis. Gold Hydrogen cost is an estimate
3. For industrial buyers, a hydrogen offtake price of €3 ($4.50) per kg would be required to incentivise hydrogen production over power generation
goldhydrogen.com.au | ASX:GHY |
9
Gold Hydrogen Limited
1(ii) Global hydrogen demand is forecast to surge
Substantial investment laying the foundation for Hydrogen use
Source: Frost & Sullivan Report - Page 29 of Gold Hydrogen Prospectus. Source: International Energy Agency, Oct-2021 (Other includes buildings, agriculture and refineries).
goldhydrogen.com.au | ASX:GHY |
10
Gold Hydrogen Limited
1. Source: USGS, 2023: https://pubs.usgs.gov/periodicals/mcs2024/mcs2024-helium.pdf
2. Air-corrected laboratory analyses for Helium purities. Refer ASX releases of 2 August 2024 and 17 October 2024. Technical Tables appended.
1(iii) Key drivers for helium
The global wholesale helium market is
expected to grow from an estimated
US$5bn in 2023 to over US$8bn in
20301
There are commercial global gas projects with significant
lower helium concentrations (>1%)
Indicatively pricing is currently approximately USD400-
500 per Mcf (thousand cubic feet)
(Source: Kornbluth Helium Consulting)
goldhydrogen.com.au | ASX:GHY |
11
Gold Hydrogen Limited
2. What We Have Achieved and Learned
12
Gold Hydrogen Limited
2) Gold Hydrogen has a significant run sheet of achievements to date
goldhydrogen.com.au | ASX:GHY |
i) Hydrogen and Helium
Identified
• 2024 drilling and well testing confirmed the presence of a Natural Hydrogen and Helium system adjacent to the historic
(1931 Ramsay Oil Bore) site at Ramsay.
• World-class purities of Natural Hydrogen and Helium1 measured during GHY drilling and testing:
• 95.8% Natural Hydrogen
• 36.9% Heliumwith evidence of Helium-3 in samples
• During exploration well testing, both Natural Hydrogen and Helium concentrations increased over time as formation
water was pumped from the wells.
• Helium-3 identified at Ramsay via noble gas analysis conducted at Oxford University.
ii) Target Zones
Identified and
Prospective Resources
Defined
• 4 main target zones were identified:
• Hydrogen: Shallow Zones A / B, Basement Zone D
• Helium: Dolomite Zone C and Basement Zone D
• Significant prospective resource estimates established by third-party consultants for both Natural Hydrogen and Helium
within PEL 687 (Yorke Peninsula).
iii) Improved H2 and He
Flow Understanding
• Improved understanding across both wells in terms of He and H2 concentrations.
iv) Aeromag 2D Seismic
Surveys
• Aeromag (aerial gravity and magnetics) and 2D seismic surveys have helped to delineate basement architecture and
structural lineaments across the Yorke Peninsula which have formed the basis for identifying new drilling and testing
locations.
v) Strategic Investment
• Promise from results shown from 2023 / 24 resulted in the supportive strategic investment of $14.5m from Toyota Motor
Corporation, Mitsubishi Gas Chemical and ENEOS Xplora.
1. Laboratory gas samples – air and nitrogen corrected. Refer ASX releases of 27 May 2024, 2 August 2024 and 17 October 2024. Tables appended.
13
Gold Hydrogen Limited
Extracted from fluid
inclusions in rock chips from
historical wells
Extracted from fluid
inclusions rock chips from
historical wells
Hydrogen from historical
wells
Extensive regional play across 7,400 km2 permit area
2(i) High purity hydrogen and helium in PEL687
Note: Ramsay 1 & 2 drilling and well test sample
results are air and nitrogen corrected. Results are
in a range up to these values. Refer ASX releases
of 31 October 2023 to 19 December 2023, 2
August 2024 and 17 October 2024. Tables
appended.
14
Gold Hydrogen Limited
2(ii) Target zones for targeted drilling have been identified
Target Zones & Resources
(Hydrogen / Helium)
• 4 main target zones identified
from drilling and testing
Ramsay 1 and 2.
• Natrual Hydrogen shows in
basement (D) and shallow
zones (A and B).
• Helium in dolomite zone (C)
and basement (D).
goldhydrogen.com.au | ASX:GHY |
Mudgas measurements
MDT
A
B
C
D
Minlaton
Fm
Parara
Limestones
Kulpara
Limestones
Kulpara
Dolomites
Winulta Fm
Basement
Ramsay Lst
Basement
(weathered)
15
Gold Hydrogen Limited
2(iii) Understanding of H2 flow has begun
Stage 2 well testing of Ramsay 2 exploration well at depths 200m to 350m1
• Narrow-gauge exploration well.
• Testing process and timeframe limited by Govt
approvals.
• H2 concentrations increased over time as the
well was dewatered, with gas to surface.
• Successful testing and data collection from
exploration well achieved.
• 2025 / 26 program designed to optimise testing
timeframes and potential outcomes (larger
well bores and pump sizes to optimise gas
recovery).
1. Graph extrapolated from ASX release of 2 August 2024. Technical Table appended.
Note: gas samples from the annulus at the wellhead. Concentrations are corrected for air and nitrogen.
goldhydrogen.com.au | ASX:GHY |
16
Gold Hydrogen Limited
2(iii) Understanding of He flow has begun
Stage 2 well testing of the Ramsay 1 exploration well
• Narrow-gauge exploration well.
• Testing process and timeframe limited by Govt
approvals.
• Helium concentrations increased over time as
the well was dewatered, with gas to surface.
• World-leading purity of Helium (36.9%1)
established, providing encouragement that the
Ramsay field could potentially support a
commercial development for Helium.
• 2025 / 26 program designed to optimise testing
timeframes and potential outcomes (larger
well bores and pump sizes to optimise gas
recovery).
1. Laboratory gas sample analyses - air (and nitrogen) corrected. Refer ASX releases of 17 October 2024.
Technical Tables appended.
2. Graph reference: ASX release release of 17 October 2024. Technical Table appended.
Results measured at the gas separator; air and nitrogen corrected.
goldhydrogen.com.au | ASX:GHY |
17
Gold Hydrogen Limited
2(iv) Ramsay 2D seismic program has helped identify optimal drilling locations
Regional 2D seismic survey acquired June - July 2024
• Historic seismic data over the Yorke Peninsula PEL
687 was extremely limited.
• The Company’s 2024 seismic data acquisition
allowed fresh interpretation of the geological
setting for PEL 687.
• 2025 well locations selected with reference to the
2024 seismic data in more optimal locations,
including up-dip from Ramsay 1 & 2.
• Ramsay 3 sited approximately 2km north-east of
Ramsay 1, and 80m up-dip from Ramsay 2, with
the seismic profile cross referenced to offset well
data.
Ramsay 2DSS was acquired in June
- July 2024 and consists of 575km
of modern 2D data covering the
Ramsay project area and the
potential exploration
opportunities.
goldhydrogen.com.au | ASX:GHY |
18
Gold Hydrogen Limited
2(v) Strategic investments from global leaders
• Gold Hydrogen undertook a 12-month strategic
process to identify partners with the capital,
technology and expertise to accelerate
development of the Company’s Natural
Hydrogen and Helium assets.
• The strategic process involved detailed due
diligence, including international site visits, data
room reviews, and multiple technical and
commercial meetings.
• The process resulted in the selection of three
global strategic partners who have now
invested in the next stage of the Company’s
growth.
• $14.5m combined initial investment.
• Placement at $0.70 per share on 3 July 2025 (being a 22%
premium to the prevailing share price).
• Establishment of strategic collaboration focused on
evaluating long-term opportunities across the Natural
Hydrogen and Helium value chain, including:
Exploration, extraction and ultimately production from the
flagship Ramsay Project in South Australia;
Evaluation of potential Natural Hydrogen supply opportunities
for mobility and industrial uses, together with transportation
fuel cell and power generation platforms;
Collaboration on a review of existing and emerging
technologies regarding the potential for future Natural
Hydrogen purification and utilisation, and potential associated
R&D projects;
Investigation of potential future commercialisation pathways,
including Green Methanol production.
19
Gold Hydrogen Limited
Through the first drilling program Gold Hydrogen made several crucial learnings
goldhydrogen.com.au | ASX:GHY |
• Ramsay 1 & 2, located nearby the 1931 Ramsay Oil Bore 1 well, confirmed the presence of
Natural Hydrogen and Helium, but more optimal well locations exist based on
subsequent new seismic data.
• Multiple prospective stacked reservoirs are present with variable fluid and reservoir
properties including Helium rich fluids in the highly permeable Kulpara dolomite reservoir.
• Seismic data and other subsurface workstreams are key to appraising the
Ramsay resource base through maturing an understanding on stratigraphy and structural
settings.
• Water in sealing units overlying Natural Hydrogen bearing reservoirs appears to
contribute to retaining Natural Hydrogen as evidenced by the increasing hydrogen
concentrations during dewatering in the 2024 well testing program.
• The size of the well bore matters for the Ramsay Project - well testing outcomes can be
optimised with larger well bores.
20
Gold Hydrogen Limited
3. Objectives and Executing on Lessons
21
Gold Hydrogen Limited
Planned objectives
goldhydrogen.com.au | ASX:GHY |
1. Further define resource
and optimise drilling
locations
2. Further optimise well
design for appraisal and
production
3. Partnerships and
downstream opportunities
4. Develop geological and
commercial model/s
• Further Prove the existence
of Natural Hydrogen and
Helium resources away from
the Ramsay 1 & Ramsay 2
well sites.
• Extract/ flow compositions
of Natural Hydrogen and
Helium to surface across the
Ramsay Project area.
• Gather further data from
drilling and logging to
enhance understanding of
the subsurface, including
reservoir characteristics.
• Well testing will inform
potential further design
optimisation for potential
future commercial
developments.
• Analysis of data and well test
results will inform reservoir
deliverability and provide
guidance for potential future
commercial developments.
• Leverage appropriate
partner technology and / or
industry specialists to
develop specific downstream
project opportunities,
including:
Helium purification
Hydrogen to Energy
Hydrogen to Green Methanol
Hydrogen to Pipeline
• Maximise data and
operational learning
opportunities for
deployment in future
Ramsay Project exploration
and appraisal
drilling campaigns.
• Develop blueprint for
exploration and appraisal
across the Company’s wider
portfolio.
The four key stages to continue to de-risk the Ramsay Project are:
22
Gold Hydrogen Limited
Executing on lessons learned
3(i) Location:
- Ramsay 2D Seismic Survey
- Up-dip
- Ramsay 3 Drilling
3(ii) Well Analysis and Application
3(iii) Water Permitting
23
Gold Hydrogen Limited
3(i) 2025 / 26 well locations: Ramsay 2D seismic survey
24
Gold Hydrogen Limited
• Ramsay 3 to be drilled first and
subsequent locations will be
subject to initial drilling results
• 2 firm + 1 contingent (2+1)
drilling campaign.
• 4 well locations high-graded.
• Vertical wells (<20 days each).
• Formation evaluation and
reservoir characteristic analysis
during drilling and further
evaluation to be conducted
during testing in 2026.
3(i) Location: up-dip
25
Gold Hydrogen Limited goldhydrogen.com.au | ASX:GHY |
• Drilling ~20 days per well plus logging.
• TD approx. 900m, including basement.
• Ramsay 3 up-dip from Ramsay 1 & 2.
• Specialist H2 / He mud-gas sampling.
• DQ 1000 mass spectrometer for real-time
formation and fluid analysis.
• Wireline logging program.
• DST on selected intervals.
• Testing program in detailed planning,
procurement and approvals phase.
2km
3(i) Location: Ramsay 3 drilling
26
Gold Hydrogen Limited goldhydrogen.com.au | ASX:GHY |
3(ii) Well analysis and application
• Well bore size for the 2025 / 26 wells will allow 7 inch diameter casing to enable
optimal conditions for well testing in Q1, 2026, whereas Ramsay 1 & 2 drilled in
2023 were narrow gauge wells with 4.5 inch casing, designed to confirm historical
results.
• Furthermore, testing of Ramsay 1 & 2 in 2024 was hampered by the limited ability
to dewater the wells due to the capacity of the pump deployed, and the restricted
approvals and testing timelines.
• The potential for dry gas is highest in the shallow zones of the 2025 / 26 wells. Any
necessary dewatering will be optimised via a significant upgrade in pump capacity,
as well as expanded approvals and operating conditions (refer next slide).
• Q1 2026 well testing will be designed to gather data to support potential future
pilot projects within the Ramsay Project area, for both Natural Hydrogen and
Helium.
27
Gold Hydrogen Limited goldhydrogen.com.au | ASX:GHY |
3(iii) Water permitting
• The potential for dry gas is highest in the shallow zones of the planned wells.
Based on the results from Ramsay 1 & 2, we have planned to manage the removal
of water from the wells during the testing program.
• The Company is working with the SA Government towards approvals to reinject
formation water via the Ramsay 1 well, drilled in 2023.
• Ongoing engagement with regulators to ensure full compliance and timely
resolution.
• Lessons learned from the 2024 well testing campaign being deployed to optimise
the potential 2026 well testing outcomes.
28
Gold Hydrogen Limited
4. Upcoming 2025/26 Work Program
29
Gold Hydrogen Limited
Upcoming Work Program
4(i) Work Program & Timeline
4(ii) Regional Application Programs
4(iii) Analysis of Natural Hydrogen Use Cases
4(iv) Analysis of Helium Usage
30
Gold Hydrogen Limited
4(i) Work program & timeline
• November 2025: Exploration Drilling & Logging Ramsay 3.
• December 2025: Exploration Drilling & Logging Second Well.
• January 2026: Exploration Drilling & Logging Third Well (to
be determined).
• First Quarter 2026: Exploration Well Testing Program to
commence.
• 2025 / 26 Program Objectives:
Delineate and confirm the presence of Natural Hydrogen and
Helium beyond the successful Natural Hydrogen and Helium gas
shows at the Company’s Ramsay 1 & 2 wells.
Continue to increase the team’s technical know-how, and to
optimize design and implementation for drilling and testing
operations to extract Natural Hydrogen and Helium to surface.
Mature the Ramsay Project via further appraisal in preparation for
potential commercial development decisions.
Assist with the development of a blueprint for future exploration
and appraisal initiatives across the Company’s wider portfolio.
• Currently $22m in cash.
• Program is more than fully funded with
current cash reserves.
• Track record of R&D cash refunds of circa
40% of project spend.
• Technical and downstream development
support available from the strategic
alliances formed with Toyota Motor
Corporation, Mitsubishi Gas Chemical and
ENEOS Xplora.
• In parallel, preliminary works commenced
on the broader regional application areas
(refer next slides).
31
Gold Hydrogen Limited
4(ii) Regional application areas – Fluid inclusion sample locations
• Testing of samples
within historic, third-
party drill cores to
determine the
existence and
locations of Natural
Hydrogen and / or
Helium occurrences.
• Results to be
combined with GA
seismic data to locate
future areas of
interest and drill
targets.
32
Gold Hydrogen Limited
4(ii) Regional application areas – GA seismic line
PELA792
PELA703 PELA702 PELA701 PELA700
A A’
A’
A
Regional Seismic line acquired by GA in 2022 (22GA-DL-1 DMOStack)
Interpretation of GA
seismic line across
application areas
enabling identification of
drill targets.
goldhydrogen.com.au | ASX:GHY |
33
Gold Hydrogen Limited
4(iii) Analysis being completed for various hydrogen use cases
01
03
01 - Hydrogen to Energy (e.g. Jenbacher) 02 - Hydrogen to Green Bio Methanol
03 - Hydrogen to Natural Gas Pipeline
goldhydrogen.com.au | ASX:GHY |
34
Gold Hydrogen Limited
4(iv) Analysis being completed for helium usage
Extraction and Transportation
• Once Helium flows at Ramsay have been
quantified, the gas will be processed in a central
facility, purified, and transported as liquid.
• The gaseous purification process uses an
extremely reliable PSA (pressure swing
adsorption) membrane technology. Proven
cryogenic technologies are utilised for
liquefaction.
• Technologies are readily available from a range
of equipment providers, including Chart
Industries.
https://www.chartindustries.com/Businesses-Brands/Cryo-Technologies
Helium to be stored and transported in a standard 40-Foot ISO Container UN Portable
Tank. This tank has a liquid Helium Capacity: ~41,640 litres. When vaporized, this
volume expands significantly – 1 litre of liquid Helium comes approximately 748 litres
of gas at standard temperature and pressure which equated to 31,150 m³ of gaseous
Helium per 40 foot container at a wholesale prices of up to USD436,000.
35
Gold Hydrogen Limited goldhydrogen.com.au | ASX:GHY |
Recap / Summary
• The data and results collected by Gold Hydrogen from the Ramsay 1 & 2 wells confirmed that
Natural Hydrogen existed at the Ramsay Project at high-purity levels of up to 95.8% together with
world-leading purities of Helium of up to 36.9%.
• Despite Ramsay 1 & 2 only being narrow-gauge exploration wells, drilled adjacent to the
historical 1931 Ramsay Oil Bore, the testing results - including recovering gas to surface