Ramsay Helium Flow Test Campaign Completed
Released
Released
Announcement PDF
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 1
20 October 2026
ASX Announcement
Ramsay Helium Testing Confirms Extensive, Productive
Reservoir - Commercial Development Planning Accelerates
as Contingent Resource Assessment Advances
Natural Hydrogen Flow-Test Results Pending
Highlights:
1. Ramsay Helium flow test campaign summary
Completed Helium flow testing across all three Ramsay wells in under three months, with no
lost time injuries and no H&S incidents.
Flowed Helium to surface, then purified and bottled it onsite - the first Helium bottled in Aus-
tralia since the Darwin plant closed in late 2023.
Scaled pumping rates sevenfold to approximately 14,000 bbl/day at Ramsay 3, the highest rate
achieved at the Ramsay Project to date.
2. Results and preliminary conclusions from the Ramsay Helium Project
A large, connected and highly productive Helium-bearing Kulpara Dolomite reservoir, con-
firmed across three wells spanning approximately 2.2 km.
Project-wide sustained / stabilised air-corrected Helium concentrations average approxi-
mately 15.2%, compared with global commercial Helium projects that can operate at concen-
trations as low as 1% where Helium is produced as a by-product.
Project-wide modelling indicates Helium gas rate potential of up to approximately 37 Mscf/day
per well, around 37% above the approximately 27 Mscf/day per well case identified in the in-
dependent Worley assessment as potentially commercially viable.
3. Next steps and near-term Catalysts
The results support further evaluation of a potential commercial Helium development using as
few as two wells, consistent with the development case identified in Worley’s independent as-
sessment, subject to resource certification, engineering, commercial and economic evaluation.
The Company is accelerating planning for a staged, modular Helium pilot designed to leverage
existing Ramsay wells, potentially reducing upfront capital requirements and shortening the
pathway to initial production.
The Company is targeting a maiden Contingent Resource sign-off in November 2026.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 2
The market backdrop remains supportive: Australia currently has no domestic Helium produc-
tion and imports 100% of the Helium it consumes, while reported long-term contract prices
have increased to greater than US$600/Mcf on an all-in plant-gate basis.
Results from the Natural Hydrogen flow testing of the Parara Limestone at Ramsay are currently
being interpreted and the Company will provide updates once an internal review is complete
and laboratory data has been received and analysed.
Gold Hydrogen Managing Director, Neil McDonald, said:
“Importantly, our appraisal flow testing confirms Helium flow rates of up to approximately 37 Mcf per day
per well, materially exceeding the case identified in Worley’s independent assessment of 27 Mcf per day
potentially commercially viable position. This is 37% above their estimate. Combined with sustained Helium
concentrations averaging approximately 15.2% across the project, these results strengthen the basis for
advancing our commercial development planning.
The market backdrop remains supportive. Australia currently has no domestic Helium production and
imports 100% of the Helium it consumes, while reported long-term contract prices have increased to greater
than US$600/Mcf.
Completing our Helium flow testing across all three Ramsay wells is a major milestone for Gold Hydrogen
and represents a significant step forward in advancing the project towards commercial development. In less
than three months, we have demonstrated Helium flow to surface across three wells spanning
approximately 2.2 kilometres, successfully purified and bottled Helium onsite, and achieved pumping rates
of approximately 14,000 barrels of fluid per day at Ramsay 3, and we know that it can achieve the 20,000
barrels fluid per day due to the appraisal that has been undertaken. These results provide compelling
evidence of the scale, continuity and productivity of the Helium-bearing reservoir.
Our focus now is on converting these results into value for shareholders. We are accelerating planning for a
staged, modular Helium pilot that could utilise our existing wells, with the objective of minimising upfront
capital requirements and shortening the pathway to initial production. We are also targeting independent
Contingent Resource sign-off in November, an important next step in progressing Ramsay towards
commercialisation.
Against a backdrop of Australia relying entirely on imported Helium, we believe Ramsay has the potential
to become an important future source of domestic supply. And with Natural Hydrogen flow-test results from
the Parara Limestone now being interpreted, we have another potentially significant opportunity ahead of
us.
We have made substantial progress in establishing the Helium opportunity at Ramsay. Our priority now is
to translate that technical success into a credible development pathway, while continuing to evaluate the
broader Natural Hydrogen potential of the project.”
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 3
Further Details
Further to the Company’s announcement of 6 October 2026, the Directors of Gold Hydrogen Limited (Gold
Hydrogen, ASX: GHY, the Company) are pleased to advise that Phase 2 of the Helium flow testing program
at the Ramsay 3 well, Ramsay Project (PEL 687), Yorke Peninsula, South Australia, has been completed. This
concludes the Helium flow testing component of the Company’s 2026 Ramsay flow test campaign, which
has now tested the Helium-bearing Kulpara Dolomite at Ramsay 1, Ramsay 2 and Ramsay 3.
Ramsay 3 – Phase 2 Helium Flow Test
Ramsay 3 is the Company’s purpose-designed, larger-diameter scale-up well. Its 7-inch cased, cemented
and perforated completion provides approximately 2.3 times the wellbore cross-sectional area of the
Ramsay 1 and Ramsay 2 wells and accommodates a high-capacity ESP rated at up to 20,000 bbl/day.
Phase 1 of the Ramsay 3 program (10 to 30 September 2026), with the ESP set at approximately 730m in
the lower section of the Kulpara Dolomite, delivered gross fluid rates of up to 13,000 bbl//day, as reported
on 6 October 2026. For Phase 2, the ESP was repositioned shallower within the 180m gross Kulpara
Dolomite reservoir, and a stepped-rate flow testing program was undertaken over a number of days.
Phase 2 Test Result Summary:
1. Gross fluid rates were increased in stages to a maximum of approximately 14,000 bbl/day – the highest
rate achieved at the Ramsay Project to date, around seven times the rates achieved at Ramsay 1 and
Ramsay 2;
2. The approximately 14,000 bbl/day rate was achieved with an implied drawdown of approximately 350
psi, consistent with the Productivity Index of approximately 40 bbl/day/psi reported for Ramsay 3 on
14 September 2026 – the highest at the Ramsay Project to date;
3. Helium was flowed to surface and separated, with an air-corrected Helium concentration of up to 12.6%
recorded during the Ramsay 3 Helium test program;
4. The well has significantly more productivity potential and current testing program suggested that flow
rates were impacted by a Productivity Index (well deliverability) which was twice the rate of that
expected;
5. The project-wide gas–water ratio presented is derived from downhole bailer sampling at Ramsay 1, as
reported on 5 August 2026;
6. Pressure, temperature and flow rate data were acquired across each rate step, adding to the Phase 1
pressure build-up data, which showed negligible pressure depletion and indicated a preliminary
drainage radius of approximately 1.25 km; and
7. Gas and water samples have been collected for independent laboratory compositional and isotopic
analysis.
Full technical details are set out in Table 3 (ASX Listing Rule 5.30). The figures stated above are preliminary
field-derived measurements and remain subject to confirmation by further independent laboratory
analysis.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 4
Project-Wide Helium Flow Test Results
With all three wells now tested, the Company is able to present, for the first time, a whole-of-project view
of the Helium-bearing Kulpara Dolomite reservoir. The key results from each well, and the project-wide
figures adopted for development planning, are summarised in Table 1.
Table 1 – Ramsay Project Helium flow test results by well (Kulpara Dolomite)
Parameter Ramsay 1 Ramsay 2 Ramsay 3 Project-wide
Well completion
4-inch slotted liner
(2023 exploration
well)
Cased and perforated
7-inch cased,
cemented and
perforated
–
ESP rated capacity (bbl/day) 2,000 2,000 20,000 –
Maximum recorded gross
fluid rate (bbl/day)
Up to 2,000 Up to 2,300 Up to ~14,000 Up to ~20,000
Productivity Index
(bbl/day/psi)
Up to ~34 Up to ~34 ~40 ~34 to ~40
Unconstraint well potential
(bbl/day)
34,000 34,000 40,000 34,000 to 40,000
Air-corrected Helium
concentration
19% 20% Up to 12.6% ~15% (average)*
In-situ gas–water ratio –
downhole bailer (scf/bbl)
~3 (2024 test) ~3 (2024 test) Not recorded ~3
Gas–water ratio – surface
samples (scf/bbl)
Up to 6.4 (2024 test) ~3 (2024 test)
Inconclusive
(assumed up to ~3)
Up to 6.4
Raw Gas rate potential
(Mscf/day)
Up to 217 Up to 102 Up to 120 Up to 250
Helium gas rate potential
(Mscf/day)
Up to 41 Up to 20 Up to 15 Up to 37
* Notes: Arithmetic average of the stabilised / sustained air-corrected Helium concentrations recorded from the Kulpara Dolomite at Ramsay
1 (19%), Ramsay 2 (20%) and Ramsay 3 (stabilised concentration of 6.5% with samples up to 12.6%), equal to 15.2%. Ramsay 2 also recorded
up to 19% air-corrected Helium from the Hiltaba Basement, which is not included in the average. Project-wide assumptions in the table are
based on the Company’s preliminary interpretation of all flow test data acquired to date.
Modelled Helium Rates for a 20,000 bbl/day Well – Project-Wide Basis
At Ramsay, Helium is carried in solution in formation water and liberated at surface by separation. Gas
production is therefore a direct function of the volume of water produced and its gas–water ratio, and
Helium production is a function of the Helium concentration of that gas.2
The Company’s previous deliverability modelling (5 August 2026) was based on Ramsay 1 data, including
an air-corrected 19% stabilised Helium concentration. With all three wells now tested, the Company has
updated this modelling on a project-wide basis, adopting the project-wide average air-corrected Helium
concentration of 15.2% (including Ramsay 3), the downhole bailer gas–water ratio of approximately 3
scf/bbl as the base case, and the surface-measured ratio from Ramsay 1 of up to 6.4 scf/bbl as an upside
case.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 5
Reservoir pressure at approximately 900m measured depth is estimated at approximately 1,280 psi on a
normally pressured basis.2
The approximately 500 to 590 psi of drawdown required to produce 20,000
bbl/day appears achievable through further optimisation of completion and design parameters, and the
14,000 bbl/day delivered by Ramsay 3 at an implied drawdown of approximately 350 psi has materially
narrowed the gap between measured and modelled rates. Moving forward, the Company believes that
further optimisation to reach a 20,000 bbl/day rate can still be achieved by improving ESP and well design.
Technical and Operational Objectives Achieved Across the 2026 Helium Campaign
The 2026 Ramsay flow test campaign was designed to measure flow rates across the Helium-bearing
formations and to provide the data required to support Contingent Resource assessment, development
planning and Front-End Engineering Design (FEED). The Helium component of the campaign has achieved
each of its key operational objectives, as summarised in Table 2.
Table 2 – 2026 Helium flow test campaign: objectives and outcomes
Campaign objective Outcome
Maximise flow of Helium to surface
from the Kulpara Dolomite
Achieved
Helium flowed to surface and separated at Ramsay 1, Ramsay 2 and Ramsay
3 using large capacity ESPs
Demonstrate onsite separation and
purification
Achieved
Quantum Technology membrane unit lifted the raw-stream Helium
concentration at Ramsay 1 from 5.6% to 50.5% (before air correction);
Helium captured, bottled and used for onsite demonstrations.1,2
Test reservoir continuity beyond a
single well
Achieved
Helium flowed from the same Kulpara Dolomite reservoir at three well
locations spanning approximately 2.2 km.3
Quantify reservoir deliverability
Achieved
Productivity Index of up to ~34 bbl/day/psi at Ramsay 1 and Ramsay 2 and
~40 bbl/day/psi at Ramsay 3, well above the 2 bbl/day/psi typical of low-
permeability reservoirs.2,4
Scale up artificial lift rates
Achieved
Pumping rates scaled from 2,000 bbl/day (Ramsay 1) to approximately
14,000 bbl/day (Ramsay 3).
Validate development-
representative well designs
Achieved
Cased and perforated completion at Ramsay 2 improved ESP efficiency by
almost three times; 7-inch Ramsay 3 design performed as intended.3,4
Acquire zonal, pressure and
reservoir data
Achieved
Zonal and Distributed Temperature Sensing (DTS) data at Ramsay 2 and
Ramsay 3; pressure build-up and stepped-rate data at Ramsay 3, with a
preliminary drainage radius of ~1.25 km.3,4
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 6
Campaign objective Outcome
Manage produced water
Achieved
Ramsay 1 repurposed and utilised as the designated re-injection well under
the campaign’s groundwater re-injection approvals.1,8
Acquire samples for laboratory
analysis
Achieved
Gas samples collected for compositional and isotopic analysis, including
Helium and Helium-3, with CSIRO and Oxford University.2
Safety
Achieved
Helium flow testing campaign completed with no lost time injuries and no
H&S incidents
Near-Term Pathway to a Contingent Resource Sign-Off
A Contingent Resource is an estimate of the quantity of Helium potentially recoverable from a known
accumulation, where a potential commercial development project has been identified. Booking a maiden
Contingent Resource is an important step for the Ramsay Project, moving it beyond Prospective Resources
and providing an independent, recognised framework for development planning, partnering and funding
discussions.
The Ramsay flow test campaign has now acquired the key dynamic data that the Company identified as
required to support this assessment: Helium flowed to surface at three wells, reservoir deliverability
quantified, Helium concentration measured under flowing conditions, reservoir continuity tested across
multiple wells and a recovery and purification route demonstrated at field scale.
The near-term pathway to a Contingent Resource sign-off comprises:
1. Laboratory confirmation – completion of all independent compositional and isotopic analysis of gas and
water samples from all three wells;
2. Integrated reservoir modelling – incorporation of the flow, pressure build-up, DTS and Productivity
Index data into the Company’s geological models, including a dissolved-phase quantitative volumetric
assessment;
3. Development project definition – definition of the modular development concept, which provides the
identified development project required under the SPE Petroleum Resources Management System
(PRMS) and its guidance for non-hydrocarbon resources, including Helium; and
4. Independent assessment and sign-off – review and certification of the Contingent Resource estimate
by an independent resource evaluator, with results to be reported in accordance with the ASX Listing
Rules, targeted for November 2026.
Accelerated Modular Helium Development Planning
As reported by the Company on 20 May 2026, the independent Worley assessment concluded that a
commercial Helium development at Ramsay may potentially be viable with as few as two wells, subject to
further technical, commercial and economic evaluation. Building on the completed flow test campaign, the
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 7
Company is accelerating planning for a staged, modular Helium pilot development designed to make
maximum use of the four Ramsay wells that have already been drilled, as illustrated in Figure 1:
Figure 1 – Indicative modular Helium development concept (schematic only, not to scale)
Modular Helium Pilot Development Components
Ramsay 2, 3, 4 – Helium producers: The opportunity to utilise existing Helium wells for an accelerated
and low-cost Phase 1 modular Helium development. The Ramsay 3 purpose-built 7-inch scale-up well
has delivered the highest flow rates (up to approximately 14,000 bbl/day) and productivity (approxi-
mately 40 bbl/day/psi) at the Ramsay Project to date. Ramsay 4 will also be considered as a new pro-
ducer and can be cased and cemented with a 7 inch casing.
Ramsay 5 – potential new development well: the Company will also assess the potential drilling of an
additional Ramsay 5 development and production well, applying the larger-diameter design validated at
Ramsay 3.
Ramsay 1 – re-injection well: Ramsay 1 has operated as the designated re-injection well during the 2026
campaign and is planned to continue in this role, returning produced formation water to the aquifer.
Modular Helium plant: a modular, skid-mounted purification plant combining membrane separation
with a pressure-swing adsorption (PSA) stage to reach commercial-grade (approximately 99%) Helium.
Vendor design and costings for a modular commercial Helium plant have been completed with Quantum
Technology Corporation and will now be further progressed following the completion of the Helium flow
testing campaign.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 8
Subject to Contingent Resource definition, the Company intends to progress an accelerated FEED for a
Helium-focused development and continues commercial discussions with technology, offtake and
distribution partners.
The development opportunity is supported by a favourable market backdrop. Australia has had no domestic
Helium production since the closure of the Darwin Helium plant in late 2023 and imports 100% of the
Helium it consumes, while global supply remains tight following the disruption at Qatar’s Ras Laffan facility.
Reported long-term Helium contract prices have increased to greater than US$600/Mcf on an all-in plant-
gate basis (refer Reference 9).
Natural Hydrogen Flow Testing of the Parara Limestone
With the Helium campaign complete, the Gold Hydrogen team are now focussed on the interpretation of
the Natural Hydrogen flow testing from the Parara Limestone at Ramsay 3.
Ramsay 3 recorded air-corrected Natural Hydrogen concentrations of up to 97% from calibrated mud gas
and isotube data during drilling. The flow test program provides the first flow data from the Natural
Hydrogen-bearing Parara Limestone in the cased and cemented Ramsay 3 well, with key objectives to:
flow Natural Hydrogen to surface from the Parara Limestone;
measure Natural Hydrogen concentrations and gas composition under flowing conditions;
acquire reservoir deliverability, pressure and flow rate data; and
collect gas samples for independent laboratory analysis.
A successful result would further demonstrate the dual-commodity potential of the Ramsay Project, with
Natural Hydrogen and Helium potentially developed from shared wells and surface infrastructure. Gold
Hydrogen will provide further updates to the market once the preliminary interpretation of data is
complete.
Important Risk Commentary
It is important to note that there remain both geological and potential development risks associated with
the Ramsay Project and the Company’s commercial and business objectives. The results described in this
announcement are from exploration and appraisal flow tests and do not confirm commercially recoverable
Helium, sustained long-term flow rates, or project economics. Field measurements reported in this
announcement have uncertainty, are preliminary and remain subject to laboratory confirmation. Project-
wide averages are arithmetic averages of results from three wells and individual well results vary, as shown
in Table 1. Modelled flow rates at 20,000 bbl/day have not been demonstrated by flow testing to date.
Exploratory flow testing of the Parara Limestone may not result in a flow of Natural Hydrogen to surface.
There is no certainty that Contingent Resources will be able to be booked, that an accelerated FEED or a
Ramsay development will proceed, or that commercial viability can be established.
Gold Hydrogen’s exploration and appraisal activities for Natural Hydrogen and Helium are regulated under
the South Australian Energy Resources Act 2000 and associated regulations. The modelling of Natural
Hydrogen and Helium reservoirs, and potential production rates, is based on industry best practice relying
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 9
on petroleum industry methods. Gold Hydrogen’s project assessment and development follows that
recommended by the Society of Petroleum Engineers and its Petroleum Resources Management System
(SPE-PRMS).
Cautionary Note on Modelled Flow Rates
The modelled flow rates are outcomes of the Company’s deliverability modelling prepared by Mr Billy Hadi
Subrata, Gold Hydrogen’s Chief Technical Officer.
The maximum rate demonstrated to date is approximately 14,000 bbl/day at Ramsay 3. Due to a range of
sub-surface and operational conditions, actual flow rates achieved may differ materially from modelled
rates. The modelled rates are not an estimate of Helium reserves or contingent resources and should not
be relied upon as such. They are forward-looking statements based on modelling work to date, and should
be read subject to the Forward Looking Statement below.
Qualified Petroleum Reserves and Resources Evaluator (QPRRE) Statement
The information in this announcement that relates to the results of the Ramsay 1, Ramsay 2 and Ramsay 3
flow tests, the derived Productivity Indices, the project-wide averages and the modelled flow rates is based
on, and fairly represents, information and supporting documentation prepared by Mr Billy Hadi Subrata,
Chief Technical Officer for Gold Hydrogen, who is a Qualified Petroleum Reserves and Resources Evaluator.
Mr Hadi Subrata has consented to the inclusion of this information in the form and context in which it
appears.
References and Previous Company Disclosures
1
ASX release “Australian First – Helium Purified and Bottled at Ramsay 1” dated 29 July 2026.
2
ASX release “Ramsay 1 Flow Test Delivers Outstanding Helium Results” dated 5 August 2026.
3
ASX release “Ramsay 2 Flow Test Confirms Continuity of the Prolific Helium-Bearing Kulpara Reservoir”
dated 25 August 2026.
4
ASX release “Interim Ramsay 3 Flow Testing Update – Strong Reservoir Deliverability” dated 14
September 2026.
5
ASX release “Ramsay 3 Advances Gold Hydrogen’s Helium Commercialisation Pathway” dated 6 October
2026.
6
ASX release “Ramsay Project Helium Commercialisation Update” dated 20 May 2026 (Worley
independent assessment).
7
ASX release “Ramsay 3 Preliminary Drilling Results” dated 2 December 2025
8
ASX release “Ramsay 2026 Exploration Well Testing Campaign – Operational Update” dated 2 July 2026.
9
https://www.gasworld.com/story/renergen-secures-first-offtake-for-south-african-Helium-
project/2252920.article/
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 10
The Company confirms that it is not aware of any new information or data that materially affects the
information included in the previous market announcements referred to above and that all material
assumptions and technical parameters underpinning those disclosures continue to apply and have not
materially changed.
Further Information
Further information on the Gold Hydrogen group, its projects, and its Board and Management can be found
on the Company’s website ( www.goldhydrogen.com.au ). Gold Hydrogen also has accounts on LinkedIn
and Twitter (@GHY_ASX), and copies of market releases will be emailed to all interested parties who
register via investorhub.goldhydrogen.com.au/auth/signup.
This announcement has been authorised for release by the Managing Director.
On behalf of the Board
Karl Schlobohm
Company Secretary
For Company Enquiries Contact:
Neil McDonald – Managing Director Karl Schlobohm – Company Secretary / CFO
nmcdonald@goldhydrogen.com.au kschlobohm@goldhydrogen.com.au
+61 7 3521 8038 +61 7 3521 8038
For Media Enquiries Contact:
Matthew Doman – Crestview Strategy
matthew.doman@crestviewstrategy.com
+61 421 888 858
Forward Looking Statement / Future Performance
This announcement may contain certain forward-looking statements and opinion. Forward-looking
statements, including aspirational forward-plans, projections, forecasts and estimates, are provided as a
general guide only and should not be relied on as an indication or guarantee of future performance and
involve known and unknown risks, uncertainties, assumptions, contingencies and other important factors,
many of which are outside the control of the Company and which are subject to change without notice and
could cause the actual results, performance or achievements of the Company to be materially different
from the future results, performance or achievements expressed or implied by such statements. Past
performance is not necessarily a guide to future performance and no representation or warranty is made
as to the likelihood of achievement or reasonableness of any forward-looking statements or other forecast.
Nothing contained in this announcement, nor any information made available to you is, or and shall be
relied upon as, a promise, representation, warranty or guarantee as to the past, present or the future
performance of Gold Hydrogen Limited.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 11
Table 3 – Ramsay 3 Helium Flow Test Program – Phase 1 and Phase 2 (ASX Listing Rule 5.30 Disclosures)
Name of well: Ramsay 3
Location (UTM zone 53
GDA2020)
UTM zone 53 GDA2020: X 749096 mE / Y 6151186 mN
Permit PEL 687
Entity’s working interest Gold Hydrogen 100%
Resources Helium
Formation Kulpara Dolomite (primary Helium target zone)
Gross thickness and net pay
thickness
180m gross primary target zone for flow testing. Perforation interval
of 105m in Kulpara dolomite.
Insufficient information is presently available to determine net pay
thickness.
Geological rock type Kulpara Dolomite
Depth of the zones tested Perforated intervals between 500m to 800m depth
Type of test and duration
Zonal Electrical Submersible Pump (ESP) flow test across the Kulpara
Dolomite. Phase 1 (ESP set at approximately 730m): 10 September
2026 to 30 September 2026, including wellbore clean-up. Phase 2 (ESP
set at approximately 366m): 5 October 2026 to 8 October 2026,
stepped-rate test.
Phase recovered Gas, water
Corrected He concentration in
gas recovered during flow test
(Other recovery and
proportions)
Stabilsed air-corrected Helium concentrations of approximately 6.5%
(up to 12.6%) were recorded during the Ramsay 3 Helium flow test
program, without purification.
Formation water produced with dissolved gas. No downhole bailer
samples were acquired; insufficient information is presently available
to determine an in-situ gas–water ratio for Ramsay 3.
Flow rates, choke size, volumes
recovered
Phase 1: gross fluid rate of up to 13,000 bbl/day, with more than
25,000 bbl of fluid recovered. Phase 2: gross fluid rate of up to
approximately 14,000 bbl/day; choke size 48/64 inch; cumulative
volume recovered of more than 11,000 bbl.
Derived Productivity Index of approximately 40 bbl/day/psi.
Insufficient information is presently available to determine raw gas
and Helium flow rates.
Fracture stimulation N/A
Material non hydrocarbons Hydrogen, Helium, Nitrogen, CO2, H2S
Information compiled by Billy Hadi-Subrata, Gold Hydrogen’s Chief Technical Officer.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 12
Table 4 – Sample Analysis Table for Ramsay 2 - 2026 Flow Test (Originally Published 25/08/2026)
Name of well: Ramsay 2 – 2026 Flow Testing
Location (UTM zone 53
GDA2020)
UTM zone 53 GDA2020: X 747,761.61 / Y 6,149,371.41
Permit PEL 687
Entity’s working interest Gold Hydrogen 100%
Resources Helium
Formation
Test 1: Kulpara Dolomite (primary Helium target zone, and ESP pump
depth), Parara Limestone. Test 2: Hiltaba Basement (Primary Helium
zone and ESP pump depth), Kulpara Dolomite, Parara Limestone
Gross thickness and net pay
thickness
180m gross primary target zone for flow testing. Perforation interval
of 24m in Kulpara dolomite.
200 m gross thickness in Hiltaba Basement. Perforation interval of 6m
into basement fracture network
Insufficient information is presently available to determine net pay
thickness.
Geological rock type Kulpara Dolomite, Limestone, Hiltaba Granitic Basement
Depth of the zones tested Perforated intervals between 219m to 1050m depth
Type of test and duration
Zonal Electrical Submersible Pump (ESP) flow tests across both the
Kulpara Dolomite and Hiltaba Basement intervals (wi