Gold Hydrogen Commences the Next Stage of Flow Testing the Ramsay
World-Class Natural Hydrogen and Helium System
Ramsay 3 Well Testing Set to Commence
HIGHLIGHTS
Gold Hydrogen Limited (ASX: GHY) has moved to Ramsay 3 to commence Natural Hydrogen and He-
lium flow testing. Workover operations are underway, and flow testing is scheduled to commence
immediately thereafter.
The Ramsay 3 well location and casing/completion have been specifically selected and designed to
optimise the appraisal and maximise flow rates for both Natural Hydrogen and Helium.
Ramsay 3 is a 7-inch diameter cased well, compared with the 4½-inch casing installed on the Ramsay
1 and Ramsay 2 wells which have been successfully flow tested.
The Ramsay 3 7-inch wellbore provides over 2.3 times the wellbore cross-sectional area to capitalise
on the strong reservoir deliverability seen at the Ramsay Project to date. This enables the use of a
substantially larger-capacity Electric Submersible Pump (ESP) of up to 20,000 bbl/day, providing a
significant increase in flow-testing capability.
To date, flow test results from Ramsay 1 and Ramsay 2 have confirmed the presence of a continuous
and laterally extensive 180m gross Helium reservoir.
The Company has already confirmed that world class Helium of up to 20% stabilised air-corrected
purities were successfully flowed to surface and separated from Ramsay 1 and Ramsay 2, including a
successful trial of the Quantum Technology Purification Equipment. Refer to attached Tables 1 and
2.
Ramsay 1 and 2 Helium flow testing indicated strong reservoir deliverability with a Productivity Index
of up to 34 bbl/day/psi, capable of raw gas rates of up to ~128 Mscf/day and Helium rates of up to
~24.3 Mscf/day from the Kulpara Dolomite.
The Ramsay Project has the potential to underpin a commercial Helium development in line with an
independent Worley Report (refer to the Company’s ASX announcement of 20 May 2026).
Contingent Resource certification is progressing and is a priority for the Company, further de-risking
the Ramsay Project.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 2
Gold Hydrogen Managing Director Neil McDonald said:
“Ramsay 3 has been designed to optimise appraisal and maximise flow rates for both Natural Hydrogen and
Helium at Ramsay. The commencement of Ramsay 3 testing is an extremely important milestone for Gold
Hydrogen. Formation evaluation has provided us with very encouraging information on the reservoir,
including favourable porosity, natural fracturing and fluid mobility, as well as supporting continuity of
important gas-bearing zones across approximately 2.3 kilometres between Ramsay 2 and Ramsay 3.
Ramsay 1 and Ramsay 2 were 4½-inch cased wells. Ramsay 3 is a 7-inch diameter cased well, providing
approximately 2.3 times the wellbore cross-sectional area. In short, we now have a bigger well, a bigger
pump and what independent analysis has identified as highly encouraging reservoir characteristics.
If we can demonstrate strong and sustained flow rates while maintaining significant Natural Hydrogen and
Helium concentrations, it could be a major step forward in establishing the commercial potential of the
Ramsay Project.
We believe the Ramsay Project has the potential to become a globally significant source of both Natural
Hydrogen and Helium, and Ramsay 3 is designed to test the scale up of that potential.”
RAMSAY 3 TESTING TO COMMENCE
Gold Hydrogen Limited (“Gold Hydrogen” or “the Company”) is pleased to announce that Natural Hydrogen
and Helium testing is due to commence at Ramsay 3 once workover operations have been completed.
The Company believes Ramsay 3 represents a major progression in the appraisal of the Ramsay Project
because it brings together two critical developments:
1. Advanced petrophysical and formation evaluation. The integration of Nuclear Magnetic Resonance
(NMR), acoustic imaging and resistivity imaging which has identified favourable reservoir characteristics
including porosity, natural fracturing and fluid mobility across the gas bearing Parara Limestone, Kulpara
Dolomite and Winulta Sandstone reservoirs at Ramsay 3;
and
2. A substantially larger wellbore and ESP system designed to scale up reservoir deliverability. The
modelled flow rates assumed from Ramsay 1 and Ramsay 2 well tests can be tested through a zonal flow
test of Ramsay 3 for both Natural Hydrogen and Helium bearing reservoirs. The downhole ESP is expected
to flow gross fluid rates of up to 20,000bbls/day from the 7-inch cemented and cased wellbore design at
Ramsay 3.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 3
RAMSAY 3 FORMATION EVALUATION
The geological case for Ramsay 3 has been strengthened by detailed formation evaluation undertaken by
the Company and its independent consultants including Baker Hughes and ImageStrat Pty Ltd.
The formation evaluation supports the interpretation that key gas-bearing zones are laterally continuous
between Ramsay 2 and Ramsay 3, approximately 2.3 kilometres apart. This provides additional support for
the Company's geological model that the Natural Hydrogen and Helium-bearing formations extend across
a substantial area rather than representing an isolated occurrence.
The NMR data provides additional formation-level information relevant to pore structure, fluid
characteristics and mobility, complementing the exceptional gas concentrations observed during drilling
and the subsequent flow-testing results. After the drilling of Ramsay 3, NMR log analysis was conducted by
Baker Hughes and Gaffney Cline energy advisory.
NMR analysis has been used widely in the gas industry identify and assess subsurface fluids including gas
and water. As shown in Figure 1 below, the log shows a strong dissolved gas effect at an interval between
682m and 690m. Ramsay 3 has a total of 105m Helium gas anomalies interpreted to be similar to this within
the Kulpara dolomite which will be perforated and flow tested as part of this campaign.
Figure 1: NMR Log analysis from Ramsay 3 highlighting an interpreted Helium anomaly
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 4
THE RAMSAY 3 WELL DESIGN
Ramsay 1 was completed with a 4½-inch slotted liner and was considered a commingled test utilising the
2,000bbl/day capacity ESP with all formations open to the borehole.
Ramsay 2 was completed with a 4½-inch cemented casing. Select depths were perforated allowing for gas
bearing intervals to be open to the borehole and the zonal test was completed using the same 2,000bbl/day
capacity ESP.
Ramsay 3 is a 7-inch diameter cased and cemented well. Select zones are being perforated initially for the
zonal Helium flow test following by a follow up Natural Hydrogen flow test. The larger diameter borehole
provides approximately 2.3 times the cross-sectional area of a 4½-inch diameter cased well. This provides
substantially greater capacity for flow-testing operations and allows Gold Hydrogen to deploy a
20,000bbl/day ESP capacity pumping system.
The larger Ramsay 3 well therefore provides an important opportunity to test the reservoir under
significantly greater flow conditions than was possible from the Company's earlier 4½-inch cased wells.
Collected flow test data, along with data acquired from Ramsay 1 and Ramsay 2 flow tests will provide key
inputs into near term independent Contingent Resource certification.
Important Risk Commentary
It is important to note that there remain both geological and potential development risks associated with
the Ramsay Project and the Company’s commercial and business objectives. Exploratory flow testing of the
Hiltaba Basement interval may not result in a flow of Helium to surface. There is no certainty that the Ram-
say 3 testing program will achieve the expected outcomes, that Contingent Resources will be able to be
booked, that an accelerated FEED or a Ramsay development will proceed, or that commercial viability can
be established.
Further Information
Further information on the Gold Hydrogen group, its projects, and its Board and Management can be found
on the Company’s website ( www.goldhydrogen.com.au ). Gold Hydrogen also has accounts on LinkedIn
and Twitter (@GHY_ASX), and copies of market releases will be emailed to all interested parties who
register via investorhub.goldhydrogen.com.au/auth/signup.
This announcement has been authorised for release by the Managing Director.
On behalf of the Board
Karl Schlobohm
Company Secretary
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 5
For Company Enquiries Contact:
Neil McDonald – Managing Director Karl Schlobohm – Company Secretary / CFO
nmcdonald@goldhydrogen.com.au kschlobohm@goldhydrogen.com.au
+61 7 3521 8038 +61 7 3521 8038
For Media Enquiries Contact:
Matthew Doman – Crestview Strategy
matthew.doman@crestviewstrategy.com
+61 421 888 858
Forward Looking Statement / Future Performance
This announcement may contain certain forward-looking statements and opinion. Forward-looking
statements, including aspirational forward-plans, projections, forecasts and estimates, are provided as a
general guide only and should not be relied on as an indication or guarantee of future performance and
involve known and unknown risks, uncertainties, assumptions, contingencies and other important factors,
many of which are outside the control of the Company and which are subject to change without notice and
could cause the actual results, performance or achievements of the Company to be materially different
from the future results, performance or achievements expressed or implied by such statements. Past
performance is not necessarily a guide to future performance and no representation or warranty is made
as to the likelihood of achievement or reasonableness of any forward-looking statements or other forecast.
Nothing contained in this announcement, nor any information made available to you is, or and shall be
relied upon as, a promise, representation, warranty or guarantee as to the past, present or the future
performance of Gold Hydrogen Limited.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 6
Table 1 – Ramsay 1 Flow Test Results (2026 Campaign). From 5 August 2026 release.
ASX Listing Rule 5.30 Ramsay 1 – 2026 Flow Test
(a) Name and type of well Ramsay 1 – vertical exploration well, flow tested with electrical
submersible pump
(b) Location, permit or lease PEL 687, Yorke Peninsula, South Australia. UTM zone 53 GDA2020: X
748,208.07 / Y 6,149,545.7
(c) Entity’s working interest Gold Hydrogen Limited 100%
(d) Net pay thickness
(conventional)
Insufficient information is presently available to determine net pay
thickness. 180m gross pay thickness in Kulpara Dolomite (Helium zone)
(e) Geological rock type Parara Limestone, Kulpara Dolomite, Granite basement
(f) Depth of zones tested 212m to 1,005m
(g) Type and duration of
test(s)
Production flow test using a 2,000 bbl/day electrical submersible
pump, commenced 25 July 2026, total duration 7 days including 5 days
of stabilised flow
(h) Hydrocarbon phases
recovered
Not applicable – no hydrocarbons recovered. Gas stream comprises
predominantly Helium, nitrogen and natural hydrogen.
(i) Other recovery and
proportions
Formation water produced at rates between 500 - 2,000 bbl/day; Gas
dissolved in water. An in-situ gas–water ratio of approximately 3
scf/bbl is calculated from the downhole bailer samples collected during
the Ramsay 1 2024 flow test. Gas-water ratios of up to 6.4 scf/bbl were
also measured from surface samples during 2024 flow testing
(j) Choke size, flow rates and
volumes
Gross fluid rate of up to 2,000 bbl/day (constrained by ESP rated
capacity, not reservoir deliverability); raw gas rate of approximately up
to 6.0 Mscf/day; Helium rate of approximately 1.14 Mscf/day; choke
size 14/64 inch; cumulative volumes recovered 3808 bbl. Derived
Productivity Index of approximately 20 bbl/day/psi at approximately
100 psi drawdown. PI of up to 34 bbl/day/psi were also calculated
(k) Fracture stimulation None
(l) Material non-hydrocarbon
gases
Helium (air-corrected concentration of up to 30%, stabilised at 19%),
Hydrogen, Nitrogen, CO2
(m) Other material
information
The well is completed with 4.5-inch slotted liner and the test was
constrained by installed pump capacity. Field measurements are
preliminary and subject to independent laboratory confirmation.
Modelled flow rates at 20,000 bbl/day are set out in Note 1 and have
not been demonstrated by flow testing.
Information compiled by Billy Hadi-Subrata, Gold Hydrogen’s Chief Technical Officer.
Gold Hydrogen Limited, Level 14, 110 Eagle Street (GPO Box 801) Brisbane, Qld 4000 | info@goldhydrogen.com.au | ABN 74 647 468 899 | 7
Table 2 – Ramsay 2 Flow Test Results. From 25 August 2026 release.
Name of well: Ramsay 2
Location (UTM zone 53
GDA2020)
UTM zone 53 GDA2020: X 747,761.61 / Y 6,149,371.41
Permit PEL 687
Entity’s working interest Gold Hydrogen 100%
Resources Helium
Formation Test 1: Kulpara Dolomite (primary Helium target zone, and ESP pump
depth), Parara Limestone. Test 2: Hiltaba Basement (Primary Helium
zone and ESP pump depth), Kulpara Dolomite, Parara Limestone
Gross thickness and net pay
thickness
180m gross primary target zone for flow testing. Perforation interval
of 24m in Kulpara dolomite.
200 m gross thickness in Hiltaba Basement. Perforation interval of 6m
into basement fracture network
Insufficient information is presently available to determine net pay
thickness.
Geological rock type Kulpara Dolomite, Limestone, Hiltaba Granitic Basement
Depth of the zones tested Perforated intervals between 219m to 1050m depth
Type of test and duration Zonal Electrical Submersible Pump (ESP) flow tests across both the
Kulpara Dolomite and Hiltaba Basement intervals (with well open
above), commenced 12 August 2026, completed 23 August 2026. Test
1, ESP at 800m depth closer to Kulpara formation, whereas Test 2, ESP
at 1002m depth in the basement
Phase recovered Gas, water
Corrected He concentration in
gas recovered during flow test
(Other recovery and
proportions)
20% He (air-corrected) from the gross 180m Kulpara Dolomite
interval, without purification
19% He (air corrected) from 200m Hiltaba basement interval, without
purification
Flow rates, choke size, volumes
recovered
Gross fluid rate of up to 2,300 bbl/day (constrained by ESP rated
capacity); choke size 13/64 inch; cumulative volumes recovered on
Test 1 - 1983 bbl; cumulative volumes recovered on Test 2 – 2702.9
bbl. Insufficient information is presently available to determine final
flow rates
Fracture stimulation N/A
Material non hydrocarbons Hydrogen, Helium, Nitrogen, CO2
Information compiled by Billy Hadi-Subrata, Gold Hydrogen’s Chief Technical Officer.
Share your feedback
Discover